Monthly Operating Repts for May 1993 for Zion Units 1 & 2
ML20036C148
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/31/1993
From: Cygan J, Joyce T
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ZAD-93-007, ZAD-93-7, NUDOCS 9306140307
Download: ML20036C148 (13)


Text

-

Commonwealth Edis n fotsh!@i$N.

Zion. Illinos 60099 Telephon3 708 / 746-2084 1

June 8, 1993 ZAD-93-007 Nuclear Regulatory Commission Document Control Desk Hashington, DC 20555

Dear Sir:

Attached is the May 1993 Operating Status Report.

t Tl P. Joyce {} /

Station Manager Zion Station TPJ/jlc Enclosure cc: Regulatory Assurance USNRC Document Control M. Hallace A. B. Davis (NRC)

T. Rieck D..Farrar D. R. Eggett INPO Div. of Eng. Health State of Illinois F. Yost NRC Inspector, Zion Operating-Engrs.

C. Y. Shiraki - Fax Master File

/

7 1 O

6 ' O C 's 9306140307 930531 PDR ADOCK 05000295 R

PDR f

~

OPERATING DATA REPORT DOCKET NO. 50-295 DATE 06/08/93 COMPLETED BY J. Cyaan j

TELEPHONE (708) 746-2084 X3169 I

a OPERATING STATUS i

1.

Unit Name: __ Zion _UDit 1 2.

Reporting Period: Q000 050193 to 24D0 053193 Notes 3.

Licensed Thermal power (MWt):

3250 4.

Nameplate Rating (Gross MWe):

1085 5.

Design Electrical Rating (Net MWe):

1040 6.

Maximum Dependable Capacity (Gross MWe): 1085 7.

Maximum Dependable Capacity (Net MWe):

1040 f

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, If Any (Net MWe):

N/A

10. Reasons for Restrictions, If Any:

N/A i

This Month Yr-to-Date Cumulative

11. Hours In Reporting Period 744.0 3.623.0 170.207.0
12. Number Of Hours Reactor Has Critical 744.0 3.623.0 116.055.5
13. Reactor Reserve Shutdown Hours 0.0 0.0 2.521.8
14. Hours Generator On-Line 744.0 3.623.0 112.579.1
15. Unit Reserve Shutdown Hours 0.0-0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2.376.699 11.513.923 328.247.214
17. Gross Electrical Energy Generated (MWH) 795.375_

3.860.814

_1Q6.424.828

8. Net Electrical Energy Generated (MWH) 767.067 3.720.759_

101.246.363

19. Unit Service Factor 100,0_

100.Q_

66ml;

20. Unit Availability Factor 100.0 100.0 66.1
21. Unit Capacity Factor (Using MDC Net) 99.1 98.7 57.2
22. Unit Capacity Factor (Using DER Net) 99.1 98.7 57.2
23. Unit Forced Outage Rate 0.Q_

0.0 16 1_

1

24. Shutdowns Scheduled Over Next 6 Months (Type Date, and Duration of Each):

Schtduled Shutdown for Refuelina Optage 10/21/93.

Stantyp_ Scheduled for 3/31/94.

25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION i

I ZCLERK-5(2) i

-OPERATING DATA REPORT DOCKET NO._50-304 DATE 06/08/93 COMPLETED BY J. Cv9an TELEPHONE (708) 746-208a_-

x3169 OPERATING STATUS 1.

Unit Name:

Zion Unit 2 2.

Reporting Period: 0000 050193 to 2400 053193 Notes i

3.

Licensed Thermal Power (MHt):

3250 4.

Nameplate Rating (Gross MHe):

1085 5.

Design Electrical Rating (Net MWe):

1040 6.

Maximum Dependable Capacity (Gross MHe):

1085 7.

Maximum Dependable Capacity (Net MWe):

1040 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through-7) Since Last Report, Give Reasons:_

N/A 9.

Power Level To Which Restricted, If Any (Net MWe):

N/A

10. Reasons for Restrictions, If Any:

N/A f

This Month Yr-to-Date Cumulative

11. Hours In Reporting Period 744.0_

3.62LO_

113ML_0_

12. Number Of Hours Reac tor Has Critical 744.0 2.354.6 116.892.3
13. Reactor Reserve Shutdown Hours 0.0 Q10_

226.1

14. Hours Generator On-line 744.0 2.354.6 113,933.6.
15. Unit Reserve Shutdorn Hours 0.0 0.Q; 0.D_
16. Gross Thermal Energ) Generated (MHH) 2.187.559,D_

6.962.596.0-

-337.654.936_

17. Gross Electrical Energy Generated (MWH) 734.008.0 2.334.469.0 108.502.404
18. Het Electrical Energy Generated (MWH)_

707.235,0L 2.240.531.0 -

1103.351.195_

19. Unit Service Factor 100.0 65.0 69.5
20. Unit Availability Factor 100 Q_

65.0 69.5

21. Unit Capacity Factor (Using MDC Net) 91.4 59.5 60.6
22. Unit Capacity Factor (Using DER Net) 91,f_-

59.5 6046_

23. Unit Forced Outage Rate 0.0 0.0 15.3
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Scheduled Shutdo_wn for Service Water Outaae 10/7/93.

Startup_icheduled for 318/94.

i

25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION ZCLERK-5(3)-

-4 UNIT SHUTDOHNS~AND POWER REDUCTIONS DOCKET NO. 50-295-UNIT NAME Zion Unit 1 L

DATE 06/08/93 COMPLETED BY J. Cygan TELEPHONE (708) 746-2084 x3169 REPORT MONTH May 1993 Duration Method of Licensee Systgm Compogent Cause & Corrective l

No.

Date Type (Hours)

Reason 2 Shutting Event Code Code Action to Down Report #

Prevent Recurrence Reactor 3 On-line for the entire reporting-period.

I 2

3 4

F: Forced Reason:

Method Exhibit G - Instructions 5: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance of Test 2-Manual Trip Entry Sheets for Licensee C-Refueling

_3-Auto Trip Event Report (LER) File D-Regulatory Restriction 4-Continued (NUREG-0161)

E-Operator Training & Licensee Examination 5-Reduced Load F-Administrative 5

G-Operational Error-(Explain)

Exhibit 1 - Same Source H-Other.(Explain)

ZCLERK-5(4)

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-304

^

UNIT NAME Zion Unit 2 DATE 06/08/93 COMPLETED BY J. Cygan TELEPHONE (708) 746-2084 x3169 REPORT HONTH May 1993 Duration Method of Licensee Systgm Compogent Cause & Corrective l

No.

Date Type (Hours)

Reason 2 Shutting Event Code Code

' Action to Down Report #

Prevent Recurrence Reactor 3 On-line for the entire reporting period.

I 2

3 4

F: Forced Reason:

Method Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance of Test 2-Manual Trip Entry Sheets for Licensee C-Refueling 3-Auto Trip Event Report (LER) File D-Regulatory Restriction 4-Continued (NUREG-0161)

E-Operator Training & Licensee Examination 5-Reduced Load F-Administrative 5

G-Operational Error (Explain)

Exhibit 1 - Same Source H-Other (Explain)

ZCLERK-5(5)

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-295 UNIT Zion Unit 1 DATE_QiLQB193 COMPLETED BY J. Cygan TELEPHONE (708) 746-2084 x3169 MONTH MAY 1993 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MHe-Net)

(MWe-Net) 1 1.0 16 17 1.045 2

908 18 1.044 3

964 19 1.009 4

LD46 20 1.038 5

1.048 21 1.048 6

1.048 22.

1.0.48 7

1.045 23 1.048

+

8 992 24 1.048 9

991 25 1.030 10 996 26 1.023 11 1.049 27 1.049 12 1.049 28 1.049 1

13 1.049 29 1.048 14 1.047 30 1.047 s

15 1.046 31 1.046 16 1.028 INSTRUCTIONS On this format, list the average daily unit power level in MHe-Net for each

-day in the reporting month. Compute to the nearest whole megawatt.

ZCLERK-5(6)

F.

AVERAGE DAILY UNIT POWER LEVEL I

DOCKET NO. 50-304 UNIT Zion Unit 2 DATE 06/08/93 COMPLETED BY J. Cygan i

TELEPHONE (708) 746-2084

_X3169 MONTH MAY 1993 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MHe-Net)

(MWe-Net) 1 1.000 17 932 2

776

.16 944 3

958 19 954 4

948 20 969 5

894 21 986 6

943 22 1.011 r

7 LO49 23 922 8

_313 24 964 9

992 25-945 10 1.039 26 939 _

11 971 27 967 12 986 28 959 13 944 29 988 4

14 1.011 30 838 15 994 31 922 16 730 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

i I

ZCLERK-5(7)

MAY 1993 f

~

SUMMARY

OF OPERATING EXPERIENCE

)

l I

UHJT 1 Unit 1, began May at 1096 MWe Power Level (99.4% Reactor Power).

There were no Load Reductions or Unit Shutdowns during the month of May. Unit 1 was continuously on line for 242 days on 5/31/93.

The Unit concluded the

[

reporting period at 1090 MWe power level (99.4% reactor power).

UNIT 2 Unit 2, began May at 1056 MWe Power Lovel (95% Reactor Power).

There were l

no Load Reductions or Unit Shutdowns oJring the month of May.

Unit 2 was i

continuously on line for 97 days on 5/31/93.

The Unit concluded the reporting period at 1060 MHe power level (95.4% reactor power).

i i

k i

f ZCLERK-5(8)

a MAY 1993 MAJOR SAFETY RELATED MAINTENANCE Esulpment Name Hork Performed (UNIT 1)

Low Discharge Pressure:

1A BA Pp Pump repaired DOS: 4/18/93 - 5/6/93 1A FH Pp Misc repairs All repairs completed 005: 5/19/93 - 5/28/93 OA Fire Pp Seal repair:

Repair completed 00S: 5/19/93 - 5/21/93 i

4 OC CC Pp Motor repair - Shield installation:

=j Hork completed & oil' changed (PH Lube) 00S: 5/19/93 - 5/24/93-COMMENT (S):

L i

t i

- 2 CLERK-5(9) i

MAY 1993 MAJOR SAFETY RELATED MAINTENANCE Egulpment_Hame Hork Performed (UNIT 2) 2A CH Pp Major Overhaul:

Overhaul completed 005: 3/1/93 - 5/12/93 2A SW Pp Major Overhaul:

005: 3/8/93 2C CD Pp Major Overhaul:

Work completed 005: 3/22/93 - 5/13/93 2A H-G Set High Vibration:

Repair completed 005: 4/18/93 - 5/14/93 2B CD Pp Repair Oil Leak:

l Pump repaired 005: 5/14/93 - 5/19/93 B

2C HDR Pp Overhaul:

005: 5/17/93 2B AF Pp 011 Cooler Leak:

011 Cooler replaced 005: 5/27/93 - 5/29/93 2D CD/CDB Pp Putp Overhaul-005:-5/26/93 l

COMMENT:

2A SW Pp scheduled RTS 6/4/93 2C HDR Pp scheduled RTS 7/22/93 2D CD/CDB scheduled RTS 7/9/93 5

ZCLERK-5(10) 1 J

~

REEUELLliG INFORMATI0lLREQUESI Questions:

1.

Name of facility.

2.

Scheduled date for next refueling shutdown.

3.

Scheduled date for restart following refueling.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If answer is yes, what, in general, will these be?

If answer is no, has the reload fuel design and core configuration been reviewed by your Plant Safety Review Committee to determine whether any unreviewed safety questions are associated with the core reload (Ref. 10 CFR Section 50.59)?

If no such review has taken place, when is it scheduled?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations associated with refueling, e.

g.,

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

7.

The number of fuel assemblies: (a) in the core and (b) in the spent fuel storage pool.

8.

The present licensed spent fuel pool storage capacity and the size of-any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

9.

The projected date of the last' refueling that can be discharged to the spent fuel pool assuming the present licensed capacity.

P P

Page 1 of 3 ZCLERK-5(11)

I Unit 1 - Answers 1.

Zion Unit 1 2.

Cycle 13 is scheduled to shutdown October 21, 1993 for refueling.

3.

Cycle 14 is scheduled to start up March 31, 1994.

4.

No Technical Specification changes are planned for Z1C14 so far.

t 5.

Not applicable or none proposed.

6.

Not applicable.

7.

The number of fuel assemblies a) in the core is 193, and b) in the spent fuel storage pool from Zion Unit 1 is 784.

[

8.

The present licensed spent fuel pool storage capacity (shared with Zion Unit 2) is 2112 fuel assemblies.

Work is in progress to rerack the Spent Fuel Pool'to increase storage capacity to 3012 assemblies.

9.

Zion Station will lose dual full core discharge capability in February 1994, at the beginning of Unit 1 Cycle 14, based on the latest Nuclear Stations Refueling Schedule. Full core discharge capability for a single core will be lost in February 1996, at the beginning of Unit 2 Cycle 15.

I i

a i

t i

t Page 2 of 3 ZCLERK-5(12)

1 i

l

.i Unit 2 - Answers 1.

Zion Unit 2 i

2.

Cycle 13 is scheduled to shutdown December 31, 1994 for refueling, j

3.

Cycle 14 is scheduled to start up March 12, 1995.

4.

No Technical Specification changes are planned for Z1C14 so far.

5.

Not applicable or none proposed.

6.

Not applicable.

7.

The number of fuel assemblies a) in the core is 193, and b) in the spent fuel storage pool from Zion Unit 2 is 840.

8.

The present licensed spent fuel pool storage capacity (shared with Zion Unit 1).is 2112 fuel assemblies. Hork is in progress to rerack the Spent Fuel Pool to increase storage capacity to 3012 assemblies.

9.

Zion Station will lose dual full core discharge capability in February 1994, at the beginning of Unit 1 Cycle 14, based on the latest Nuclear Stations Refueling Schedule. Full core discharge capability for a single core will be lost in February 1996, at the beginning of Unit 2 Cycle 15.

h t

.e i

i 5

i Page 3 of 3 i

ZCLERK-5(13)

.