Responds to NRC 810817 Request for Info Re Implementation of NUREG-0609 & 0612 Positions.Positions Will Be Implemented During Final Design of Plant
ML20030C421
Person / Time
Site: Atlantic Nuclear Power Plant PSEG icon.png
Issue date: 08/18/1981
From: Haga P
OFFSHORE POWER SYSTEMS (SUBS. OF WESTINGHOUSE ELECTRI
To: Tedesco R
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-02, REF-GTECI-A-36, REF-GTECI-RV, REF-GTECI-SF, RTR-NUREG-0609, RTR-NUREG-0612, RTR-NUREG-609, RTR-NUREG-612, TASK-A-02, TASK-A-2, TASK-A-36, TASK-OR FNP-PST-066, FNP-PST-66, NUDOCS 8108260088
Download: ML20030C421 (1)


Text

'

FNP-PST-066 Off2hore Power Systems o.o 1E m ru / vg_ x u

na m:

3y4 4cy V-h August 18, 1981 I'

519B F M5'f Mr. R. L. Tedesco, Assistant 3

fM ve Director for Licensing r, u#p Division of Licensing D,,

S' U.S. Nuclear Regulatory Commission

'^

7920 Norfolk Avenue

/TS Bethesda, MA 20852 Re:

Docket No. STN50-437; Request for Information oirator Generic Task Action Plans A-2 and A-36 Power Systems Technology

Dear Mr. Tedesco:

This letter is in response to the request for information transmitted by your letter of August 17, 1981. Offshore Power Systems has reviewed NUREG-0609, " Asymmetric Blowdown Loads on PWR Primary Systems" and NUREG-0612, " Control of Heavy Loads at Nuclear Power Plants". On the basis of our review we agree to implement the Staff positions set forth in these documents during the final design of the Floating Nuclear Plant.

Reference to Sections 9.1.4 and 15.5.3 of the Plant Design Report will demonstrate that Offshore Power Systems has already given consideration to the general concerns addressed in both NUREG-0609 and NUREG-0612.

Ve truly ycurs, n

P. B. Haga CC:

V. W. Campbell A. R. Collier

/lel i

KO

//O 8108260088 810818 PDR ADOCK 05000437 A