Responds to NRC Re Violation Noted in IE Insp Repts 50-317/80-26 & 50-318/80-22.Corrective Actions:Tech Spec Change Proposed & Plant Procedures Changed to Ensure That Requirements Are Met Prior to Stopping Cooling Flow
ML19345H020
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/13/1981
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19345H019 List:
References
NUDOCS 8104300048
Download: ML19345H020 (3)


Text

_

(V m

A BALTIMORE GAS AND ELECTRIC CHARLES CENTER + P.O. BOX 1475 BALTIMORE. MARYLAND 21203 ARTHun E. LUNDVALL..Jm.

vice Passioast sveny March 13, 1981 i

U.S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406 ATTENTION:

Eldon J. Brunner, Chief Reactor Operations and Nuclear Support Branch i

Gentlemen:

This refers to your Inspection Report 50-317/80-26; 50-318/80-22, which transmitted one item of apparent noncompliance with NRC requirements.

Enclosure (1) to this letter is a written state-ment in reply to that item in your letter of February 17, 1981.

Should you have further questions regarding this reply, we will be pleased to discuss them with you.

.Very truly yours,

/

/

Guds&

, /.

A. E. Luddvall, Jr. f Vice President-Supply AEL/ RED /gla Enclosure (1) 81043000{1b

o Mr. E. J. Brunner March 13, 1981 STATE OF MARYLAND:

TO WIT:

CITY OF BALTIMORE:

Arthur E. Lundvall, Jr., being duly sworn states that he is Vice President of the Baltimore Gas and Electric Company, a corporation of the State of Maryland; that he provides the foregoing response for the purnoses therein set forth; that the statements are true and correct to the best of his knowledge, information, and belief; and that he was authorized to provide the response on behalf of said Corporation.

WITNESS my Hand and Notarial Seal:

& L.

V /

z i

} Notary Public My Commission Expires:

'% IL f

/, /h [1

[

y cc:

J. A. Biddison, Esquire G. F. Trowbridge, Esquire Director, Office of Inspection & Enforcement i

ENCLOSURE (1)

REPLY TO APPENDIX A 0F NRC INSPECTION REPORT 50-317/80-26; 50-318/80-22 The circumstances leading to this event have been reviewed with the Operations personnel who were involved.

Additionally, all licensed personnel have been informed of the details of this event.

A Facility Change Request has been initiated to change Technical Specification 3.10.5 to require that as a Limiting Condition for Operation, the charging pumps be deenergized and the charging flow paths closed prior to stopping shutdown cooling flow pursuant to this Technical Specification.

It is expected that this proposed change to the Technical Specifications will be submitted to the Nuclear Regulatory Commission no later than May 29, 1981.

Finally, appropriate plant procedures have been changed to en1ure that both the Limiting Conditions for Operation of Technical Specification 3.10.5 and the Surveillance Requirements of Technical Specification 4.10.5, are met prior to stopping shutdown cooling flow to conduct local leak rate testing of penetration number 41.

+