Press Release-IV-19-013, NRC Issues Confirmatory Order to Wolf Creek Nuclear Operating Company
ML19210C076 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 07/19/2019 |
From: | Office of Public Affairs Region IV |
To: | |
Category:Press Release | |
References | |
Press Release-IV-19-013 | |
Download: ML19210C076 (1) | |
Similar Documents at Wolf Creek | |
---|---|
Category:Press Release
MONTHYEARML24214A2372024-07-18018 July 2024
[Table view]News Release-IV-24-012: NRC Names New Resident Inspector at the Wolf Creek Nuclear Power Plant ML23166A0372023-03-14014 March 2023 News Release-23-023: International Safety Review Team Visits Wolf Creek Nuclear Power Plant Press Release-IV-21-005, NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants2021-04-30030 April 2021 Press Release-IV-21-005: NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants Press Release-IV-20-010, NRC Names New Senior Resident Inspector at the Wolf Creek Nuclear Power Plant2020-07-20020 July 2020 Press Release-IV-20-010: NRC Names New Senior Resident Inspector at the Wolf Creek Nuclear Power Plant Press Release-IV-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants2020-06-22022 June 2020 Press Release-IV-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants Press Release-IV-19-016, NRC Names New Resident Inspector at the Wolf Creek Nuclear Power Plant2019-09-30030 September 2019 Press Release-IV-19-016: NRC Names New Resident Inspector at the Wolf Creek Nuclear Power Plant Press Release-IV-19-013, NRC Issues Confirmatory Order to Wolf Creek Nuclear Operating Company2019-07-19019 July 2019 Press Release-IV-19-013: NRC Issues Confirmatory Order to Wolf Creek Nuclear Operating Company Press Release-IV-19-010, NRC to Hold Public Meeting to Discuss 2018 Performance of Wolf Creek Nuclear Power Plant2019-04-30030 April 2019 Press Release-IV-19-010: NRC to Hold Public Meeting to Discuss 2018 Performance of Wolf Creek Nuclear Power Plant Press Release-18-063, NRC Proposes $232,000 Fine to Wolf Creek Nuclear Operating Corporation2018-12-18018 December 2018 Press Release-18-063: NRC Proposes $232,000 Fine to Wolf Creek Nuclear Operating Corporation Press Release-18-008, NRC Issues Annual Assessments for Nation'S Nuclear Plants2018-03-0505 March 2018 Press Release-18-008: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-IV-16-019, NRC Schedules Regulatory Conference to Discuss Apparent Violation at Wolf Creek Nuclear Generating Station2016-09-0606 September 2016 Press Release-IV-16-019: NRC Schedules Regulatory Conference to Discuss Apparent Violation at Wolf Creek Nuclear Generating Station Press Release-IV-15-024, NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant2015-08-17017 August 2015 Press Release-IV-15-024: NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant Press Release-IV-15-023, NRC Names New Senior Resident Inspector at Wolf Creek Nuclear Power Plant2015-08-17017 August 2015 Press Release-IV-15-023: NRC Names New Senior Resident Inspector at Wolf Creek Nuclear Power Plant Press Release-IV-15-016, NRC to Conduct Open House on June 24 in New Strawn, Kan., to Discuss 2014 Safety Performance of Wolf Creek2015-06-18018 June 2015 Press Release-IV-15-016: NRC to Conduct Open House on June 24 in New Strawn, Kan., to Discuss 2014 Safety Performance of Wolf Creek Press Release-IV-15-010, NRC Says Wolf Creek Nuclear Plant Has Improved Work Environment2015-04-0808 April 2015 Press Release-IV-15-010: NRC Says Wolf Creek Nuclear Plant Has Improved Work Environment Press Release-IV-14-023, NRC to Meet with Officials to Discuss Wolf Creek Nuclear Plant2014-09-23023 September 2014 Press Release-IV-14-023: NRC to Meet with Officials to Discuss Wolf Creek Nuclear Plant ML14183B3302014-07-0202 July 2014 Press Release No. IV-14-016: NRC Issues White Finding to Wolf Creek Press Release-IV-14-011, NRC to Meet with Officials to Discus Performance of Wolf Creek Nuclear Plant2014-06-18018 June 2014 Press Release-IV-14-011: NRC to Meet with Officials to Discus Performance of Wolf Creek Nuclear Plant Press Release-IV-14-007, NRC Schedules Regulatory Conference to Discuss Apparent Violation at Wolf Creek Nuclear Plant2014-04-23023 April 2014 Press Release-IV-14-007: NRC Schedules Regulatory Conference to Discuss Apparent Violation at Wolf Creek Nuclear Plant Press Release-IV-14-001, NRC to Meet with Officials from Wolf Creek Nuclear Plant2014-01-15015 January 2014 Press Release-IV-14-001: NRC to Meet with Officials from Wolf Creek Nuclear Plant Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-IV-13-022, NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant2013-07-29029 July 2013 Press Release-IV-13-022: NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant Press Release-IV-13-010, NRC to Discuss 2012 Performance Assessment for Wolf Creek Nuclear Plant2013-04-0404 April 2013 Press Release-IV-13-010: NRC to Discuss 2012 Performance Assessment for Wolf Creek Nuclear Plant Press Release-IV-13-008, NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant2013-03-12012 March 2013 Press Release-IV-13-008: NRC Names New Resident Inspector at Wolf Creek Nuclear Power Plant Press Release-IV-12-052, NRC to Meet with Wolf Creek Nuclear Operating Co2012-11-29029 November 2012 Press Release-IV-12-052: NRC to Meet with Wolf Creek Nuclear Operating Co Press Release-IV-12-040, NRC Issues a Yellow Finding to Wolf Creek Nuclear Plant in Connection with Loss of Off-Site Power Event2012-09-21021 September 2012 Press Release-IV-12-040: NRC Issues a Yellow Finding to Wolf Creek Nuclear Plant in Connection with Loss of Off-Site Power Event Press Release-12-099, NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants2012-09-0606 September 2012 Press Release-12-099: NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants Press Release-IV-12-022, NRC to Hold Open House June 26 for Wolf Creek Nuclear Plant2012-06-15015 June 2012 Press Release-IV-12-022: NRC to Hold Open House June 26 for Wolf Creek Nuclear Plant Press Release-IV-12-007, NRC to Hold Public Meeting to Discuss Results of Augmented Inspection Conducted at the Wolf Creek Nuclear Plant2012-02-23023 February 2012 Press Release-IV-12-007: NRC to Hold Public Meeting to Discuss Results of Augmented Inspection Conducted at the Wolf Creek Nuclear Plant Press Release-IV-12-005, NRC to Send Augmented Inspection Team to Wolf Creek Nuclear Generating Station2012-01-25025 January 2012 Press Release-IV-12-005: NRC to Send Augmented Inspection Team to Wolf Creek Nuclear Generating Station Press Release-IV-11-047, NRC Begins Special Inspection at Wolf Creek Nuclear Plant2011-10-24024 October 2011 Press Release-IV-11-047: NRC Begins Special Inspection at Wolf Creek Nuclear Plant Press Release-IV-11-046, NRC to Meet with Wolf Creek Nuclear Power Plant Officials2011-10-21021 October 2011 Press Release-IV-11-046: NRC to Meet with Wolf Creek Nuclear Power Plant Officials Press Release-IV-11-009, NRC to Discuss 2010 Performance Assessment for Wolf Creek Nuclear Plant2011-03-29029 March 2011 Press Release-IV-11-009: NRC to Discuss 2010 Performance Assessment for Wolf Creek Nuclear Plant Press Release-IV-10-037, NRC to Hold Public Meeting with Wolf Creek Nuclear Operating Co2010-11-19019 November 2010 Press Release-IV-10-037: NRC to Hold Public Meeting with Wolf Creek Nuclear Operating Co Press Release-IV-10-025, NRC Conducting Special Inspection at Wolf Creek Nuclear Plant2010-06-21021 June 2010 Press Release-IV-10-025: NRC Conducting Special Inspection at Wolf Creek Nuclear Plant Press Release-IV-10-021, NRC to Hold Public Meeting to Discuss 2009 Performance of Wolf Creek2010-04-28028 April 2010 Press Release-IV-10-021: NRC to Hold Public Meeting to Discuss 2009 Performance of Wolf Creek Press Release-IV-09-032, NRC Conducting Special Inspection at Wolf Creek Nuclear Plant2009-09-21021 September 2009 Press Release-IV-09-032: NRC Conducting Special Inspection at Wolf Creek Nuclear Plant Press Release-IV-09-022, NRC Names New Resident Inspector at Wolf Creek Generating Station2009-06-19019 June 2009 Press Release-IV-09-022: NRC Names New Resident Inspector at Wolf Creek Generating Station Press Release-IV-09-010, NRC to Discuss 2008 Performance Assessment for Wolf Creek Nuclear Plant2009-03-30030 March 2009 Press Release-IV-09-010: NRC to Discuss 2008 Performance Assessment for Wolf Creek Nuclear Plant Press Release-08-213, NRC Approves License Renewal for Wolf Creek Nuclear Power Plant for an Additional 20 Years2008-11-20020 November 2008 Press Release-08-213: NRC Approves License Renewal for Wolf Creek Nuclear Power Plant for an Additional 20 Years Press Release-08-154, NRC Advisory Committee on Reactor Safeguards to Meet Sept. 4-6 in Rockville, MD2008-08-19019 August 2008 Press Release-08-154: NRC Advisory Committee on Reactor Safeguards to Meet Sept. 4-6 in Rockville, MD Press Release-08-096, NRC Finds No Significant Impacts from Extended Operation of Wolf Creek Nuclear Plant2008-05-16016 May 2008 Press Release-08-096: NRC Finds No Significant Impacts from Extended Operation of Wolf Creek Nuclear Plant Press Release-IV-08-018, NRC to Discuss 2007 Performance Assessment for Wolf Creek Nuclear Plant2008-05-13013 May 2008 Press Release-IV-08-018: NRC to Discuss 2007 Performance Assessment for Wolf Creek Nuclear Plant Press Release-IV-08-006, NRC Conducting Special Inspection at Wolf Creek Nuclear Plant2008-01-16016 January 2008 Press Release-IV-08-006: NRC Conducting Special Inspection at Wolf Creek Nuclear Plant Press Release-IV-07-036, - NRC to Hold Public Meetings on Draft Environmental Impact Statement for Wolf Creek License Renewal Application2007-09-19019 September 2007 Press Release-IV-07-036 - NRC to Hold Public Meetings on Draft Environmental Impact Statement for Wolf Creek License Renewal Application Press Release-IV-07-012, NRC to Discuss 2006 Performance at Wolf Creek Nuclear Plant2007-04-30030 April 2007 Press Release-IV-07-012: NRC to Discuss 2006 Performance at Wolf Creek Nuclear Plant Press Release-07-034, - NRC Issues Confirmatory Action Letters on Welds to Group of PWR Nuclear Power Plants2007-03-12012 March 2007 Press Release-07-034 - NRC Issues Confirmatory Action Letters on Welds to Group of PWR Nuclear Power Plants Press Release-IV-06-027, NRC Staff to Hold Two Public Meetings to Discuss License Renewal Process for Wolf Creek Nuclear Plant2006-12-13013 December 2006 Press Release-IV-06-027: NRC Staff to Hold Two Public Meetings to Discuss License Renewal Process for Wolf Creek Nuclear Plant Press Release-06-148, NRC Announces Opportunity to Request a Hearing on License Renewal Application for Wolf Creek Nuclear Power Plant2006-12-0505 December 2006 Press Release-06-148: NRC Announces Opportunity to Request a Hearing on License Renewal Application for Wolf Creek Nuclear Power Plant Press Release-06-127, NRC Announces Availability of License Renewal Application for Wolf Creek Nuclear Generating Station2006-10-10010 October 2006 Press Release-06-127: NRC Announces Availability of License Renewal Application for Wolf Creek Nuclear Generating Station 2024-07-18 |
Text
No: IV-19-013 July 19, 2019
Contact:
Victor Dricks, 817-200-1128 NRC Issues Confirmatory Order to Wolf Creek Nuclear Operating Company The Nuclear Regulatory Commission has issued a Confirmatory Order to the Wolf Creek Nuclear Operating Co., documenting mutually agreed-upon actions to implement programs designed to prevent willful misconduct by employees.
Following an investigation at the Wolf Creek nuclear power plant in Burlington, Kan., the NRC determined that a maintenance worker and a supervisor falsified a record regarding the cleaning and inspection of the reactors control rod drive mechanisms on Oct. 31, 2016. One apparent violation of NRC requirements is described in an April 2 NRC inspection report.
Company officials requested the Alternative Dispute Resolution process with the NRC to discuss corrective actions. The process uses a neutral mediator with no decision-making authority to assist the NRC and its licensees in reaching an agreement.
Following a meeting on May 30 with company officials, the NRC issued a Confirmatory Order documenting actions the company has agreed to take.