ML17262A534

From kanterella
Jump to navigation Jump to search
Proposed Tech Specs,Revising Action Statements for Offsite & Onsite Power Sources Available for Operation of Plant Auxiliaries
ML17262A534
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/20/1991
From:
ROCHESTER GAS & ELECTRIC CORP.
To:
Shared Package
ML17262A531 List:
References
NUDOCS 9107110203
Download: ML17262A534 (31)


Text

ATTACHMENT A Revise the Technical Specification pages as follows:

Remove insert Table of Contents (i) Table of Contents (i) 3.0-1 3.0-1 3.0-2 3.0-2 3.0-3 3.0-3 3.0-4 3.0-4 3~1 3 3 ~ 1 3 3+7 J. 3 ~ 7 1 3 ~7 2 3 ~ 7 2 3e7 3 3 ~ 7 3 3.7-4 3.7-4 3.7-5 3.7-6 3~7 7 3.8-2 3.8-2 4.6-1 4.6-1 4.6-1a 4.6-2 4.6-2 4.6-2a 4.6-2a 4.6-4 4.6-4 4.6-5 4.6-5 4.6-5A 4.6-5A 9$ 07$ $ 0203 9i0620 PDR AGOCK 05000244 P PDR

TABLE OF CONTENTS Pacae 1.0 DEFINITIONS 2.0 SAFETY LIMITS AND LIMITING SAFETY SYSTEM SETTINGS 2~1 1 2.1 Safety Limit, Reactor Core 2.1-1 2.2 Safety Limit, Reactor Coolant System Pressure 2.2-1 2.3 Limiting Safety System Settings, Protective Instrumentation 2 3 1

~

3.0 LIMITING CONDITIONS FOR OPERATION 3.0 Applicability 3.0-1 3.1 Reactor Coolant System 3~1 1 3.1.1 Operational Components 3~1 1 3.1.2 Heatup and Cooldown F 1-5 3.1.3 Minimum Conditions for Criticality 3.1-18

3. 1. 4 Maximum Coolant Activity 3 ~ 1 21 3.1.5 Leakage 3.1-25 3.1.6 Maximum Reactor Coolant Oxygen, Fluoride, and Chloride Concentration 3 ~ 1 31 3.2 Chemical and Volume Control System 3~2 1 3.3 Emergency Core Cooling System, Auxiliary Cooling Systems, Air Recirculation Fan Coolers, Containment Spray and Charcoal Filters 3~3 1 3.4 Turbine Cycle 3. 4-1 3.5 Instrumentation System 3.5-1 3.6 Containment System 3.6-1 3.7 Auxiliary Electrical Systems 3 7 1

~

3.8 Refueling 3.8-1 3.9 Plant Effluents 3.9-1 3.10 Control Rod and Power Distribution Limits 3.10-1 3.11 Fuel Handling in the Auxiliary Building 3.11-1 3.12 Movable In-Core Instrumentation 3.12-1 3.13 Shock Suppressors (Snubbers) 3 13 1

~

3.14 Fire Suppression System 3.14-1 3.15 Overpressure Protection System -3.15-1 3.16 Radiological Environmental Monitoring 3.16-1 4.0 SURVEILLANCE REQUIREMENTS 4.1 Operational Safety Review 4.1-1 4.2 Inservice Inspection 4.2-1 4.3 Reactor Coolant System 4.3-1 4.4 Containment Tests 4.4-1 4.5 Safety Injection, Containment Spray and Iodine Removal Systems Tests 4.5-1 4.6 Preferred and Emergency Power Systems Periodic Tests 4.7 Main Steam Stop Valves 4.7-1 Amendme No. 24 Proposed

" 3.0 LIMIT CO 0 FOR OPERATION APPLICABILITY 3.0.1 In the event a Limiting Condition for Operation and/or associated action requirements cannot be satisfied because of circumstances in excess of those addressed in the specification, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> action shall be initiated to place the unit in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> (i.e., a total of seven hours), and in at least cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> (i.e., a total of 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />) unless corrective measures are completed that permit operation under the permissible action statements for the specified time interval as measured from initial discovery or until the reactor is placed in a mode in which the specification is not applicable. If the action statement corresponding to the Limiting Condition for Operation that was exceeded contains time limits to hot and cold shutdown that are less than those specified above, these more limiting time limits shall be applied. Exceptions to these requirements shall be stated in the individual specifications.

3.0.2 When a system, subsystem, train, component or device is determined to be inoperable solely because its emergency power source is inoperable, or solely because its preferred power source is inoperable, it may be considered operable for the purpose of satisfying the requirements of its applicable Limiting Condition for Operation, provided:

Amendme No. 24 3.0-1 Proposed

(1) i orresponding preferred o .mergency power source is operable; and (2) all of its redundant system (s),

subsystems (s), 'rain (s), component (s) and device (s) are operable, or likewise satisfy the requirements of this specification. Unless both conditions (1) and (2) are satisfied within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, the unit shall be placed in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in at least cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. This specification is not applicable in cold shutdown or refueling modes.

Basis Specification 3.0.1 delineates the ACTION to be taken for circumstances not directly provided for in the ACTION statements and whose occurrence would violate the intent of the specification. For example, Specification 3.3.2 requires two Containment Spray Pumps to be operable and provides explicit action requirements if one spray pump is inoperable. Under the terms of Specification 3.0.1, if both of the required Containment Spray Pumps are inoperable, the unit is required to be in at least hot shutdown within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in at least cold shutdown in the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. These time limits apply because the time limits for one spray pump inoperable (6 gl hours to hot shutdown,,wait 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> then 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> to cold shutdown) are less limiting. As a further example, Specification 3.3.1 requires each Reactor Coolant System accumulator to be operable and provides explicit'ction requirements if one accumulator is if J

inoperable. Under the terms of Specification 3.0.1, more than one accumulator is inoperable, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> action shall be initiated to place the unit in at least hot shutdown within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and cold Amend No. 24'.0-2 shutdown within an additional 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. The time limit of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> I

Proposed

tb hot shutdown and 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> to cold shutdown do not apply because the time limits for 1 accumulator inoperable are more limiting. It is assumed that the unit is brought to the required mode within the required times by promptly initiating and, carrying out the appropriate action statement.

Specification 3.0.2 delineates what additional conditions must. be.

satisfied to permit operation to continue, consistent with the action statements for power sources, when a preferred or emergency power source is not operable. It allows operation to be governed by the time limits of the action statement associated with the Limiting Condition for Operation for the preferred. or emergency power source, not the individual action statements for each system, subsystem, train, component or device that is determined. to be inoperable solely because of the inoperability of its preferred. or emergency power source.

For example, Specification 3.7.2.1.a requires in part that two emergency diesel generators be operable. The action statement provides for a maximum out-of-service time when one emergency diesel generator is not operable. If the definition of operable were applied without consideration of Specification 3.0.2, all systems, subsystems, trains, components and devices supplied by the inoperable emergency power source would. also be inoperable. This would, dictate invoking the applicable action statements for each of the applicable Limiting Conditions for Operation. However, the provisions of Specification 3.0.2 permit the time limits for continued operation to be consistent with the action statement for the inoperable emergency diesel generator instead, provided the other specified. conditions are satisfied. In this case, this would mean that the corresponding Amen nt No. 24 3.0-3 Proposed

" preferred power rce must be operable, an ll redundant systems, subsystems, trains, components, and devices must be operable, or otherwise satisfy Specification 3.0.2 (i.e., be capable of performing their design function and have at least one preferred or one emergency power source operable) . If they are not satisfied, shutdown is required in accordance with this specification.

Amend No. 24 3.0-4 Proposed

(iii) residual heat removal loop A."

(iv) residual heat removal. loop B.*

Except during steam 'generator crevice cleaning operations, at least one of the coolant loops listed in paragraph 3.1.1.1.e hall be, in operation while. RCS temperature is less than 350'F. However, both reactor coolant pumps and residual. heat removal pumps. may be de-energized. for up to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> provided 1) no operations. are permitted that would cause dilution of the reactor coolant system boron-concentration, and 2) core outlet temperature is maintained. at least. 10'F below saturation temperature.

g, If the conditions of. 3.1.1.1.e. are not met, immediately initiate corrective action. to return the required loops to operable status, and if not in cold shutdown already, be in'cold.shutdown..within,24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

h. If the conditions of 3.1.1.1.f are not met, then suspend all operations invo1ving a reduction. in boron concentration. of the Reactor Coolant. System and.

immediately initiate corrective. action to. return the required coolant loop to operation.

  • The preferred or emergency. power source may be inoperable while in.

cold shutdown.

Amendm No. 24 3~1 3 Proposed

3.7 AUXILIARY ELECTRICAL SYSTEMS A licabilit Applies to the availability of electrical power for the operation of plant auxiliaries.

~b'o define those conditions of electrical power availability necessary to provide for the continuing availability of engineered. safeguards.

3.7.1 S ecification 3.7.1.1 With fuel in the reactor vessel, the following conditions are to be met:

a. One independent offsite power source operable, or backfeed through unit auxiliary transformer 11; and
b. One train of 480-volt buses (14 and 18, or 16 and 17) operable; and
c. One diesel generator operable with onsite supply of 5,000 gallons, of fuel available and. either buses 14 and 18, or 16 and 17, capable of being supplied from that diesel generator.
d. One battery and one dc system, and at least 150 amps of battery charger capacity to the battery must be operable.

3.7.1.2 Actions To Be Taken If Conditions of 3.7.1.1 Are Not Met:

With less than the above minimum required power source operable, immediately suspend all operations involving positive reactivity changes, core alterations, movement of Amen No. 3 3%7 1 Proposed

irradiated. fuel and. initiate corrective action to restore the required power sources to operable status.

3.7.2 S ecification 3.7.2.1 The reactor coolant system shall not be taken above the'ode indicated unless the following conditions are met:

a. Above cold shutdown;
1. One independent, offsite power source operable.
2. the 480-volt buses 14 and 18 (Train A) and buses 16 and 17 (Train B) are energized.
3. the two diesel generators're operable with onsite supply of 5,000 gallons of. fuel available for each diesel generator.

4,. both batteries, and both dc systems are operable.

5. at least 150 amps of battery charging capacity for each DC system that is in service.
b. Above 350'F ~
1. All conditions of 3.7.2.1a above are met; and
2. Two offsite sources (34.5 kv-4160 volt station service transformers-, 12A with dedicated circuit.

751,. and 12B with dedicated circuit 767) are operable.

3.7.2.2 Actions To Be Taken If Conditions of 3.7.2.1 Are Not Met:

a. Operation above. 350 F may continue with one offsite source inoperable, provided all remaining conditions of 3.7.2.1 are; met..
b. With one or both independent offsite sources operable.,

and one diesel generator, inoperable above cold shutdown,, demonstrate. the operability. of the'emaining diesel generator by:

Amendm No. 4 3 ~7 2 Proposed

1. Performing the surveillance requirements identified in Specifications 4.6.1.b.4 and 4.6.1.b.6 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter and restore the inoperable diesel generator to operable status within 7 days; OTHERWISE:
2. Reduce to a mode equal to or below hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
c. With one safety related 480V Bus (i.e., bus 14 or 16 or 17 or 18) de-energized, re-energize the bus within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or reduce to a mode equal to or below hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />, unless corrective actions are complete that permit continued operation (i.e., the bus is returned. to service).
d. With both independent offsite sources inoperable, both diesel generators must be operable. In addition, restore one independent offsite source within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, or reduce to a mode equal to or below hot, shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to an RCS temperature les's than or equal to 350'F within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
e. Operation above cold shutdown may continue if less than 150 amps of battery charging capacity is available to one dc system, provided at. least 150 amps of battery charging capacity is available to each dc system within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. If not available, reduce to a mode equal to or below hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

3~7 3 Proposed

Basis for 3.7.1 and 3.7.2:

The electrical systems equipment is arranged so that no single failure can inactivate enough safeguards equipment to jeopardize the plant safety. The 480-volt safeguards equipment is arranged on 4 safeguards buses. The 4160-volt equipment (none of which is safety-related), is supplied from 4 buses.

Two separate offsite sources supply station service power to the plant.

The plant auxiliary equipment is arranged electrically so that redundant safeguards loads receive power from separate sources. In the event that 1 offsite source is not available, the remaining offsite source is capable of supplying both trains of safeguards loads. Safeguards loads such as safety injection pumps, containment fans, residual heat removal pumps, and motor control centers 1C and 1D are divided between the 480-volt buses No. 14 and 16. Redundant loads including service water pumps are supplied by buses No. 18 and

17. Together these buses form the Train A and B redundant Class 1E sources.

offsite I

AC power for safeguards equipment originates from both and onsite sources. The operability of these power sources and associated distribution systems ensures that sufficient power will be available to supply the safety-related. equipment required for (1) the 3.7-4 Proposed

+

~

~

safe shutdown o he plant, and (2) the mi ation and control of accident conditions within the plant.

When the RCS is above cold shutdown, both emergency diesel generators are required to be operable. The two diesel generators have sufficient capacity to start and run all the engineered safeguards equipment at design loads. The safeguards equipment operated from one diesel generator can adequately cool the core and maintain the containment pressure within the design value for any loss of coolant incidents The minimum diesel fuel oil inventory is maintained to assure that both diesels can carry the design loads of required engineered safeguards equipment for at least 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />, or for one engineered safety feature train for 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />, or for operation under hot standby non-accident conditions for 111 hours0.00128 days <br />0.0308 hours <br />1.835317e-4 weeks <br />4.22355e-5 months <br />."'ommercial oil supplies and trucking facilities exist to assure deliveries within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

The offsite power source consists of separate dedicated 34.5 kV-4160 volt station service transformers served by dedicated 34.5 kV lines (12A transformer with dedicated circuit 751, or 12B transformer with dedicated circuit 767) in operable status. Either offsite source of power can supply all auxiliary loads and transfer can be accomplished within the time constraints of GDC 17. Thus, GDC 17 is explicitly met.

With fuel in the reactor vessel a minimum of one offsite source, one onsite source of AC power and one DC power train are required. The offsite power source may be provided by one of three configurations:

3. 7-5 Proposed
1. Transformer served by a dedicated 3 kV line (circuit 751), or
2. Transformer 12B served by a dedicated 34.5 kV line (circuit 767), or
3. Backfeed through unit auxiliary transformer 11.

The offsite power source is the preferred source of AC power.

Operability of an offsite source requires that one station service transformer served by a dedicated 34.5 kV line is operating and providing power to the unit. The emergency diesel generator provides power upon loss of the offsite source. One emergency diesel generator with 5,000 gallons of fuel can provide power to a minimum level of engineered safeguards equipment for 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> (the required safeguards loads at cold shutdown/refueling are significantly less than during power operation) . One operable diesel fuel oil transfer pump is required to supply fuel from one of the two fuel storage tanks to the day tank of the operable diesel generator. With less than one offsite and one onsite AC source of power available and one DC power train, no operations involving positive reactivity changes, core alterations, and movement of irradiated fuel shall occur.

Battery chargers with at least 150 amps capacity shall be in service for each battery so that the batteries will always be at full charge.

This ensures that adequate dc power will be available.

The plant can be safely shutdown without the use of offsite power since all vital loads (safety systems, instruments, etc.) can be supplied from the emergency diesel generators and the station batteries.

3.7-6 Proposed

P

" The two diesel nerators, each capable supplying safeguards loads, and the station auxiliary transformers provide four separate sources of power immediately available for operation of these loads.

Thus, the power supply meets the single failure criteria.

References (1) UFSAR Section 9.5.4 307 7 Proposed

least one source range neutron- flux monitor shall be in service.

d. least one residual heat removal loop shall be in operation.*
e. Immediately before reactor vessel head removal and while loading and unloading fuel from the reactor, the minimum boron concentration of 2000 ppm shall. be maintained. in the primary coolant system and. checked by sampling'wice, each shift.

Direct communication. between the control. room and the refueling cavity manipulator crane shall be available whenever changes in core geometry are taking place.

g In addition to the requirements of- paragraph.3.8.1,.d, while in the refueling mode with less than 23 feet of water above the top of the reactor'essel flange, two residual heat removal loops shall be operable.*

During movement of fuel or control rods within the reactor vessel cavity, at least 23 feet of water shall be maintained over the top of the reactor. vessel.

  • Either. the preferred. or the emergency power source may be inoperable for each residual heat, removal. loop.

3.8-2 Proposed

4:6 Preferred and Emer enc Power S stems Periodic Tests A licabilit Applies to periodic testing and surveillance requirements of the preferred and emergency power systems.  !

To verify that the preferred and emergency power systems will respond promptly and properly when required.

S ecification'he following tests and. surveillance. shall be performed: as.

stated:

4.6.1 Diesel Generators At least one diesel, generator shall be demonstrated operable:

a. During cold or refueling shutdown at- least once per 31 days by:
1. Verifying the diesel starts. from norma1 standby conditions,, and attains- rated voltage and frequency; Each diesel generator shall be demonstrated operable:
b. Except during. cold..or refueling shutdown at least once per 31 days by:
1. Verifying the fuel. level in. the day tank.,
2. Verifying a minimum. oi1 storage. of 5.,000 gallons:

for each, generator is onsite.

3. Verifying the fuel transfer pump. can; be started.

and. transfer fuel from the storage system to.the day tank.

4. Verifying the diesel. starts. from normal standby conditions, and attains rated voltage and frequency.
5. Verifying the generator is synchronized, loaded. to at least 1950 kw but less than the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating.

of 2250 kw and operates for at least. 60 minutes but less than 120. minutes.

6. Verifying the diesel generator is aligned; to provide standby power to the associated, emergency buses.

4.6-1 Proposed

c. The tests in Specification 4.6.1b will be performed, prior to exceeding. cold shutdown if the time since, the last test exceeds 31 days.
d. At least once per 92, days by verifying that- a. sample, of diesel fuel from the fuel storage tank is within the acceptable. limits. specified. in. Table 1 of. AS'975'-78 when checked for viscosity-, water and sediment.
e. At least once per. 18 months during shutdown by:  !
1. Inspecting the diesel in accordance with the manufacturer's recommendations for this class of-standby service.
2. Verifying the generator capability to reject a load, of 295 KW- without tripping.
3. Simulating a. loss of offsite power in conjunction with a safety injection test signal and:

(a) Verifying de-energization of the emergency buses and load. shedding from the emergency buses.

(b) Verifying" the diesel starts from normal.

standby condition on the auto.-start.. signal, energizes the automatically connected emergency loads. with the. following maximum breaker. closure- times after the initial starting signal for. Trains. A and. B not. being.

exceeded.

A B Diesel plus Safety Injection 20 sec. 22 sec Pump plus RHR Pump All Breakers 40 sec 42 sec and. operates for > five minutes while its.

generator is loaded with emergency loads..

(c) Verifying that all diesel generator trips, except'ngine overspeed, low lube oil pressure, and overcrank, are automatically bypassed upon a safety.'njection'ctuation signal.

4.6-2 Proposed

4. This test mav also serve to concurrently meet the requirements of 4.6.l.a and b.

4-6-2a Proposed

c ~ At each time data is recorded, new data shall be compared with old to detect signs of deterioration.

d. Each =battery shall be subjected to a load test within a twelve-month period. from the last load test; however-,

to permit the load test to coincide with a scheduled refueling, the period may extend- for an additional three'months. The battery voltage as a function. of time shall be monitored to establish that the. battery performs as expected during heavy discharge'nd that all electrical connections are tight.

e. Each battery shall be subject to a discharge test at least once per 60 months. The purpose of this test is to show that the battery capacity is at least. 80% of the manufacturer's recommendations.. When performed; this discharge. test may substitute for the load. test.

The discharge test shall be performed annually for any battery that shows signs of degradation. Degradation is indicated when the battery capacity drops more than.

10-o'f rated. capacity from its. average. on previous discharge tests, or is below 90-o of the manufacturer's rating.

4.6.3 Pre ferred (Offsite Power Su lies.

Eac h offsite power source. shall be demonstrated- operable:

a ~ At least. once per 7 days by:

1. Verifying, nominal voltage, indications. on the high-voltage side of transformers. 12A and 12B; and on the 4160 volt buses 12A. and 12B.
2. Verifying 4160 volt circuit breakers 12AX or 12BX, AND 12AY or 12BY are open.
3. Verifying tie breakers. 52/BT16-14 and 52/BT17-18 are open when plant. mode..is above 200'P.
b. At least once per 18 months by transferring. unit power supply to 4160 volt buses. 12A and. 12B from the normal circuit, i.e., transformer 12A for bus 12A and transformer 12B for bus 12B to the alternate, circuit, i.e., transformer 12B for bus. 12A and transformer 12A for bus 12B.

Amendm .

No. 14 4. 6-4 Proposed

Basis The tests specified are designed to demonstrate that the diesel generators will provide power for operation of equipment. They also assure that the emergency generator system controls and the control systems for the safeguards equipment will function automatically in the event of a loss of all normal 480V AC station service power.

"'he test frequency specified will be often enough to identify and correct any mechanical or electrical deficiency before it can result in a system failure. The fuel supply and starting circuits and controls are continuously monitored and any faults are indicated by alarms. An abnormal condition in these systems can be identified without having to test the diesel generators.

Periodic tests are also specified to demonstrate that the offsite power sources will provide power for operation of equipment.

Offsite power source operability requires correct breaker alignment and indicated power availability from the two preferred power circuits, 767 and 751, to the 4160 volt buses. These requirements are met by monitoring nominal voltage indications on the high-voltage side of transformers 12A and 12B; and on the 4160 volt buses 12A and Offsite power source independence requires separate 4160 volt circuits supplying power to the 4160 volt buses. Interlocks prevent concurrent closure of 12AX and 12BX, OR 12AY and 12BY; and surveillance is specified to ensure separation is maintained.

Amen t No. 14 4.6-5 Proposed

s

" Furthermore, to sure independence between dundant Class 1E 480 volt buses 14 and 18 (Train A) and buses 16 and 17 (Train B), tie breakers 52/BT16-14 and 52/BT17-18 are required to be open when the plant mode is above 200 F. Once tie breakers are open, interlocks prevent closure when independent and redundant buses are energized.

Station batteries may deteriorate with time, but precipitous failure is extremely unlikely. The surveillance specified is that which has been demonstrated over the years to provide an indication of a cell becoming unserviceable long before it fails, and to ensure that the battery capacity is acceptable.

The equalizing charge, as recommended by the manufacturer, is vital to maintaining the ampere-hour capability of the battery. As a check upon the effectiveness of the equalizing charge, the battery should be loaded rather heavily and the voltage monitored as a function of time. lf a cell has deteriorated or if a connection is loose, the voltage under load will drop excessively indicating replacement or maintenance.

The minimum permissible on-site fuel inventory, 10,000 gallons, (5,000 gallons for each generator), is sufficient for operation under loss-of-coolant accident conditions of two engineered safety features trains for 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />, or for one train for 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />, or for operation under hot standby non-accident conditions for 111 hours0.00128 days <br />0.0308 hours <br />1.835317e-4 weeks <br />4.22355e-5 months <br />.

"'eferences (1) UFSAR, Section 8.3 (2) UFSAR, Section 9.5.4 Amendm No. 14 4.6-5A Proposed

ATTACHMENT B The purpose of this Amendment is to incorporate additional Specifications and Action Statements regarding required operability of the Ginna Station Auxiliary Electrical Systems. Zn particular, additional Specifications and Action Statements have been added the modifications being made to the offsite power system. to'ddress The reconfiguration will increase the. availability margin of the offsite system by dedicating. a 34.5kV 4160 volt transformer to each of the two offsite transmission lines. The detailed changes are listed on Table 1.

Additional requirements have been added including required. actions based on reactor coolant system operation above and below cold shutdown, and specific power source operability requirements. Those new power source operability requirements are considered more conservative than previous specifications while also more explicit.

During plant startup, all available power sources are required. to provide power for engineered safeguards. and auxiliary cooling system.

The format has been modified to identify separate specifications and actions.

Minor changes have been made to the periodic test requirements for the emergency power supplies. The changes have been made to clarify the diesel generator testing requirements prior to exceeding cold shutdown. This. is a conservative change as previously the. testing was required for completion prior to exceeding 5O power. Periodic testing requirements to verify operability of the offsite. power sources previously unidentified within. the Technical Specifications-.

have been added. These testing requirements are consistent with Standard Technical, Specifications..

i Previously, the offsite power supply from the transmission grid. to.

Ginna Station consisted of two independent 34.5kV transmission lines; each capable .,of serving a single 4160 volt Station Auxiliary.

transformer (Unit 12A). Transformer 12A served a dual purpose in that it was used as a startup source and was also a dedicated offsite source for all the Class 1E. equipment The design as it existed, was less reliable in that the loss of 12A transformer. resulted in the reliance on two onsite diesel generators until such time as the Unit Auxiliary Transformer (Unit 11) could be backfed through the 115kV system. Backfeeding the Unit Auxiliary Transformer is. considered a delayed access source. and results in the long-term reliance on the diesel generators and the batteries for maintaining safe shutdown loads.

Although the offsite power system met the requirements of all existing licensing commitments, the operating margin could. be improved. The modified. system provides additional. margin by dedicating two independent offsite power sources with separate transformers.

This Technical Specification Amendment addresses specific requirements and-actions resulting from the modification, and further defines those time requirements previously unspecified within the Technical Specifications.

B-1

Specifications 3.7.1 and 3.7.2 have been created to identify the

'uxiliary electrical system requirement depending upon reactor coolant system temperature conditions. The specifications proposed identify system temperature requirements more restrictive than those currently existing. This has been done. to make them consistent with temperature limitations existing for other safety system operations.

Section 3.7.1 identifies the Specifications and actions to be taken when fuel is in the reactor for AC and DC power. The. specifications identify the operability requirements for, offsite and emergency power during reduced temperature operations with fuel in the reactor vessel. One (1) onsite, one (1) offsite, and one (1) dc system will be available during periods of operation not covered by Section 3.7.1.

Previous technical. specifications identified no specific requirements regarding operation limitations for conditions below power operation including refueling activities. Section 3.7.1.1 and. the action specified in Section 3.7.1.2 identify requirements more conservative than the existing requirements. They have been added. to provide the operators with clear specifications when less than normal power supplies are available.

The actions specified within Sections 3.7.2.2.a, b and c identify the emergency power operability and plant operations. requirements based.

upon independent offsite power source operability. The plant operation alternatives are progressive with. prudent time requirements identified based upon both the potential safety impact of the reduced power availability configuration. while allowing some time to make repairs. Allowable times are consistent with Standard Technical Specifications and. also consider. the safety implications of unwarranted plant cycling. Actions specified in Section 3.7.2.2.b.l permit operation with one diesel generator inoperable providing the operability of the remaining diesel generator is demonstrated utilizing periodic tests every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. This configuration is allowed for a period not to exceed seven (7) days in order to permit time to effect repairs. Periodic testing of the remaining diesel generator in this manner versus continuous running provides the assurances of diesel generator operability without the adverse impact of continuously running the diesel generator.

The action specified in, Section 3.7.2.2.a allows. power operation to continue following the loss of one station service transformer, provided all remaining conditions are met.. The preferred (offsite) electrical system reliability with one offsite source available has.

been proven, as it has existed since original plant licensing.

also more conservative than existing technical It specifications is as power operation was previously allowed to continue with no offsite power sources available.

The actions specified within Section 3.7.2.2.d identify the emergency power operability requirements with both offsite power sources inoperable. Prudent maximum out-of-service duration for both offsite sources of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> was chosen to both minimize .this mode of operation, while allowing some time to make repairs.

B-2

~

~

Section 4.6.1 ha een modified to require p odic (monthly) diesel generator testing during cold and refueling shutdown modes,

'consistent with operability requirements for those modes. This change is considered conservative as previously no cold or refueling shutdown testing was required.

Section 4.6.1.d.3(c) has been changed to clarify diesel generator trip testing. RGGE has determined that the words "loss of voltage on injection actuation signal" are the emergency bus and/or safety misleading since there is no bypass of protective trips on loss of voltage. Bypass of protective trips is caused only by SI. The origin of the words "loss of voltage on the emergency bus and/or" are not explicitly known. A description of diesel generator trips and bypasses provided by letter from L.D. White (RG&E) to A. Schwencer (NRC), dated May 16, 1977, makes no mention of an undervoltage bypass. A License Amendment request of November 16, 1977 states that the "Standard Tech Specs published by the NRC have been used as guidance in preparation of the proposed Technical Specification."

The current Standard Tech Specs (p. 3/4 8-5) includes the words "loss of voltage on the emergency bus concurrent with a safety injection signal" to verify the automatic bypass feature. RGGE meets this requirement with test procedure RSSP-2.2. There is no technical basis to bypass the "overcurrent" and "reverse power" trips on a loss of voltage to the emergency bus, since this would not be consistent with the accident condition assumption that an SI signal actuation is generated. Unnecessary risk to the diesel generator would be created if these two trips were bypassed in this case.

deleted the words "loss of voltage on the RG&E therefore has emergency'bus and/or" from Section 4.6.1.d.3(c) .

Section 4.6.2.c no longer specifies detecting signs of abuse through the comparison of new and old test data. Abuse, as a cause of deterioration, need not be specified within the plant Technical Specifications.

Section 4.6.3 has been created to address the surveillance requirements for the preferred (offsite) power supplies.

Section 4.6.3.a identifies verifications every 7 days for emergency power capacity and capability from the offsite power supplies. In addition, correct tie breaker alignment verification is specified to ensure independence between the redundant 480 volt safeguards buses.

These requirements are consistent with Standard Technical Specifications and more conservative than existing Technical Specifications.

In accordance with 10CFR50.91, these changes to Technical Specifications have been evaluated to determine the facility in accordance with the proposed if the operation of amendment would:

1. involve a significant increase in the probability or consequences of an accident previously evaluated; or
2. create the possibility of a new or different kind of accident previously evaluated; or
3. involve a significant reduction in a margin of safety.

B-3

These proposed anges do not increas the probability or consequences of a previously-evaluated accident or create a new or

'different kind of accident. Furthermore, there is no reduction in

'he margin of safety for any Technical Specification. The detailed are described in Table 1.

changes Therefore, Rochester Gas and Electric submits that the issues associated with this Amendment request are outside the criteria of 10CFR50.91; and a no significant hazards finding is warranted.

B-4

TABLE 1 Change Effect

1. Table of Contents revised See Section 4.6.

to include Preferred Power System Periodic Tests.

2. Section 3.0.2 Bases states No technical. change.

e::ample in 3.7.1.d. New reference example is 3.7.2.1.a.

Terminology change from "normal" to "preferred" due to the addition of a second.

offsite circuit. Footnotes on pages 3.1-3 and 3.8-2 also changed to reflect this.

Typographical error in time to cold shutdown requirement of-3 - 0. 1 in example in bases is corrected.

3. Reformat Specifications Minimum requirements for into Section 3.7.1, with fuel in theany'peration Specification Reactor Coolant reactor vessel are included in System operation with fuel in. Section 3.7.1. All specifica-the reactor vessel and, Section tions including actions for 3.7.2, Specifications Reactor operation. with the reactor.

oolant System Operation above above colcL shutdown are cold shutdown. Appropriate included in Section 3.7.2.

Specification and, Action Statements listed within. each section.

4. Proposed. Section 3.7.1.1 New additional Technical; addresses Electric Power Specifications. There were Systems requirements with the previously no electrical power with fuel in the reactor system Technical Specifications vessel. Actions to be taken or actions applicable to low are in Section 3.7.1.2. temperature operations.
5. Section 3.7.2.1 includes Increased. operating the addition of station service availability margin through the transformer 12B with dedicated addition of requirements for circuit 767 operable. Two operation requiring additional diesel generators are transformer operability.

-'dentified independently with Increased. clarity regarding required 5,000 gallon fuel diesel operability is supply. 4160 volt buses specified. Applicability o energized has been deleted. this specification. is increased Specification. applicability from reactor criticality to cnanged from anytime the anytime RCS is above cold reactor is critical to anytime shutdowIi ~

RCS temperature is above 350'F for offsite power, and above cold- shutdown for emergency sources.

'6. Section 3.7.2.2.a similar to Power operation may continue.

existing 3.7.2.a. with one station service transformer operable vs. the station service transformer inoperable.

7. Section 3.7.2.2.b'ddresses Comparable. to previous diesel generator emergency Specification 3.7.2.b with power operability, time, and. increased specificity provided action requirements with one for operability determinations independent offsite source and shutdown requirements.

operable and(or one diesel Removed the option of generator inoperable.. continuous operation of the diesel generators due to the adverse effects of such operation, and. to provide increased consistency with Standard. Technical Specifications.

8. Section 3.7.2.2.c addresses New addition Technical action requirements. with one Specification action safety related 480V bus de- requirement. The action energired. requirements. are consistent with action requirements of 3.0.6 for loss of a train power system and more stringent than Standard Technical Specifica-tion action requirements.
9. Section 3.7.2.2.d addresses New additional Technical emergency power operability and Specification action limiting time and action. requirements power operation when offsite with both independent offsite. power is not available. Based:

sources in operable. upon Standard Tech. Specs.

10. Section 3.7.2.2.e is Minor clarifying word changes, similar'o previous Section are included.

3.7.2.c.

11. Section 4.6 modified to Broader periodic testing identify periodic tests for requirements to address both preferred (offsite) power emergency and preferred system in lieu of emergency (offsite) power supply power system periodic tests operability. Based upon only. Standard Tech. Specs.
12. Section 4.6.1 modified to New This is an additional add requirement for monthly surveillance requirement for testing of at least one diesel emergency. diesel generator generator during cold or testing during shutdown refueling shutdown-. conditions. Previously there were no shutdown testing requirements for the diesel generators..
13. Section 4.6.1.b.2 oil Minor clarifying oil storage storage requirements redefined requirements per diesel for each diesel generator. generator.

t gf I>

'>14. Section 4.6.l.b modified to Increased requirements require testing prior to requiring earlier diesel exceeding cold shutdown in lieu generator operability periodic of 5-o power. testing during startup operations.

15. Specification Clarifies test requirements for 4.6.1.d.3A(c) is comparable to automatic bypass of diesel previous Specification generator trips. .Loss of 4.6.1.d.3(c) except that voltage on the emergency bus statement "loss of voltage on does not cause an automatic the emergency bus and/or" has bypass of protective trips.

been deleted.

16. Specification 4.6.1.d.4 New This addition Technical allows for satisfying the Specification is considered monthly diesel generator test more stringent than previous requirements by performance of Specifications since previously the more stringent 18 month no monthly testing of the requirements diesel generators was required below 5% power.
17. Section 4.6.3 added to New additional Technical identify periodic test Specification. There were requirements for offsite power. previously no periodic test requirements for offsite power sources.

lg