ML16082A455

From kanterella
Jump to navigation Jump to search
Response to Extension Request for Determination of Denial of Non-Cited Violation
ML16082A455
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/22/2016
From: Richard Skokowski
NRC/RGN-III
To: Hardy J
Entergy Nuclear Operations
Lambert, Kenneth
References
Download: ML16082A455 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 March 22, 2016 Mr. Jeffery A. Hardy Regulatory Assurance Manager Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION

Dear Mr. Hardy:

This is in response to your letter, dated March 11, 2016, requesting an extension of time to determine whether Entergy will contest the Non-Cited Violation (NCV) regarding the failure to perform a required Title 10 Code of Federal Regulations (CFR) 50.59 evaluation for declassification of the chemical and volume control system. The NCV was documented in U.S. Nuclear Regulatory Commission (NRC) Integrated Inspection Report 05000255/2015004, dated February 12, 2016. Your letter requested an additional 60 days from March 11, 2016, to make your determination.

I have been authorized, after consultation with the Director, Office of Enforcement, to grant Entergy 60 days from March 11, 2016, to determine whether the NCV will be contested.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and in the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Richard A. Skokowski Enforcement/Investigations Officer Docket No. 50-255 License No. DPR-20 cc: Distribution via LISTSERV

March 22, 2016 Mr. Jeffery A. Hardy Regulatory Assurance Manager Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION

Dear Mr. Hardy:

This is in response to your letter, dated March 11, 2016, requesting an extension of time to determine whether Entergy will contest the Non-Cited Violation (NCV) regarding the failure to perform a required Title 10 Code of Federal Regulations (CFR) 50.59 evaluation for declassification of the chemical and volume control system. The NCV was documented in U.S. Nuclear Regulatory Commission (NRC) Integrated Inspection Report 05000255/2015004, dated February 12, 2016. Your letter requested an additional 60 days from March 11, 2016, to make your determination.

I have been authorized, after consultation with the Director, Office of Enforcement, to grant Entergy 60 days from March 11, 2016, to determine whether the NCV will be contested.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and in the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Richard A. Skokowski Enforcement/Investigations Officer Docket No. 50-255 License No. DPR-20 cc: Distribution via LISTSERV DISTRIBUTION:

See next page ADAMS Accession Number ML16082A455 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME Lambert Skokowski DATE 03/17/16 03/22/16 OFFICIAL RECORD COPY

Letter to Mr. Jeffery A. Hardy from Mr. Richard A. Skokowski dated March 22, 2016

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION DISTRIBUTION:

RidsSecyMailCenter Resource OCADistribution Victor McCree Michael Johnson Patricia Holahan Nick Hilton Cynthia Pederson Darrell Roberts Daniel Dorman Catherine Haney Marc Dapas Edward Williamson Susan Vrahoretis Bill Dean Jennifer Uhle Lauren Casey Brice Bickett David Gamberoni John Kramer Holly Harrington Hubert Bell Kevin Fowler David DAbate Kimyata Morgan Butler RidsNrrPMPalisades Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Richard Skokowski Allan Barker Harral Logaras Viktoria Mitlyng Prema Chandrathil Kenneth Lambert Paul Pelke Magdalena Gryglak Sarah Bahksh Carole Ariano Linda Linn DRPIII DRSIII Carmen Olteanu RidsOemailCenter OEWEB Resource ROPassessment.Resource@nrc.gov

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 March 22, 2016 Mr. Jeffery A. Hardy Regulatory Assurance Manager Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION

Dear Mr. Hardy:

This is in response to your letter, dated March 11, 2016, requesting an extension of time to determine whether Entergy will contest the Non-Cited Violation (NCV) regarding the failure to perform a required Title 10 Code of Federal Regulations (CFR) 50.59 evaluation for declassification of the chemical and volume control system. The NCV was documented in U.S. Nuclear Regulatory Commission (NRC) Integrated Inspection Report 05000255/2015004, dated February 12, 2016. Your letter requested an additional 60 days from March 11, 2016, to make your determination.

I have been authorized, after consultation with the Director, Office of Enforcement, to grant Entergy 60 days from March 11, 2016, to determine whether the NCV will be contested.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and in the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Richard A. Skokowski Enforcement/Investigations Officer Docket No. 50-255 License No. DPR-20 cc: Distribution via LISTSERV

March 22, 2016 Mr. Jeffery A. Hardy Regulatory Assurance Manager Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION

Dear Mr. Hardy:

This is in response to your letter, dated March 11, 2016, requesting an extension of time to determine whether Entergy will contest the Non-Cited Violation (NCV) regarding the failure to perform a required Title 10 Code of Federal Regulations (CFR) 50.59 evaluation for declassification of the chemical and volume control system. The NCV was documented in U.S. Nuclear Regulatory Commission (NRC) Integrated Inspection Report 05000255/2015004, dated February 12, 2016. Your letter requested an additional 60 days from March 11, 2016, to make your determination.

I have been authorized, after consultation with the Director, Office of Enforcement, to grant Entergy 60 days from March 11, 2016, to determine whether the NCV will be contested.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room and in the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Richard A. Skokowski Enforcement/Investigations Officer Docket No. 50-255 License No. DPR-20 cc: Distribution via LISTSERV DISTRIBUTION:

See next page ADAMS Accession Number ML16082A455 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME Lambert Skokowski DATE 03/17/16 03/22/16 OFFICIAL RECORD COPY

Letter to Mr. Jeffery A. Hardy from Mr. Richard A. Skokowski dated March 22, 2016

SUBJECT:

RESPONSE TO EXTENSION REQUEST FOR DETERMINATION OF DENIAL OF NON-CITED VIOLATION DISTRIBUTION:

RidsSecyMailCenter Resource OCADistribution Victor McCree Michael Johnson Patricia Holahan Nick Hilton Cynthia Pederson Darrell Roberts Daniel Dorman Catherine Haney Marc Dapas Edward Williamson Susan Vrahoretis Bill Dean Jennifer Uhle Lauren Casey Brice Bickett David Gamberoni John Kramer Holly Harrington Hubert Bell Kevin Fowler David DAbate Kimyata Morgan Butler RidsNrrPMPalisades Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Richard Skokowski Allan Barker Harral Logaras Viktoria Mitlyng Prema Chandrathil Kenneth Lambert Paul Pelke Magdalena Gryglak Sarah Bahksh Carole Ariano Linda Linn DRPIII DRSIII Carmen Olteanu RidsOemailCenter OEWEB Resource ROPassessment.Resource@nrc.gov