CFR71.95 Report - Failure to Observe Certificate of Compliance #9168 Conditions for the 8-120B Cask
ML15229A173
Person / Time
Site: Surry, North Anna, 07109168  Dominion icon.png
Issue date: 08/11/2015
From: Clark G
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, NRC/NMSS/SFST
References
15-387
Download: ML15229A173 (4)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 August 11, 2015 ATTN: Document Control Desk Serial No.15-387 Director, Division of Spent Fuel Storage and NLOS/TJS R0 Transportation Docket Nos. 50-338,339 Office of Nuclear Material Safety and Safeguards 50-280,281 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 License Nos. NPF-4,7 DPR-32,37 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 10 CFR 71.95 REPORT - FAILURE TO OBSERVE CERTIFICATE OF COMPLIANCE

  1. 9168 CONDITIONS FOR THE 8-120B CASK Virginia Electric and Power Company (Dominion) is submitting this report pursuant to 10 CER 71.95(a)(3) regarding instances in which the conditions of approval in the Certificate of Compliance (CoC) #9168 for the EnergySolutions 8-120B cask were not observed when making shipments from North Anna Power Station (NAPS) and Surry Power Station (SPS).

This report is based on a 10 CFR 71.95 report notification to 8-120B cask users by the certificate holder, EnergySolutions, which Dominion received on July 21, 2015. This notification triggered the 60-day reporting requirement which is addressed by this submittal.

EnergySolutions originally reported the details of the potential failure to meet all requirements of CoC #9168, including corrective actions being taken by EnergySolutions, to the NRC by Letter CDI5-0149, dated June 24, 2015, from Daniel B. Shrum (EnergySolutions) to Mark Lombard (NRC),

Subject:

10 CFR 71.95 Report on the 8-120B Cask. [ADAMS Accession No. ML15202A058]

The enclosed notification is applicable to the past use of the 8-120B cask by Dominion facilities NAPS and SPS, Dominion records indicate that NAPS made a total of three shipments and SPS made a total of four shipments using the 8-1 20B cask. Details of these shipments are included in the attachment.

In their June 24, 2015 letter to the NRC, EnergySolutions stated there were no safety consequences from performing vent pre-shipment leak tests that may not have provided the required test sensitivity. Additionally, there will be no further tests made using the suspect gaskets since EnergySolutions has replaced all of the suspect gaskets with a modified version that does not have the potential to reduce the test sensitivity.

Serial No.15-387 Docket Nos. 50-338,339,280,281 10 CFR 71.95(a)(3) Report Page 2 of 2 If you have any questions or require additional information, please contact Mr. Thomas Szymanski at (804) 273-3065.

Sincerely, Gianna C. Clark Vice President - Nuclear Support Services

Attachment:

Dominion Shipments Using the 8-120B Cask Commitments made in this letter: None cc: Dr. V. Sreenivas NRC Project Manager - NAPS US NRC, One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Ms. Karen Cotton NRC Project Manager - SPS US NRC, One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector - NAPS NRC Senior Resident Inspector - SPS EnergySolutions LLC Attn: Daniel B. Shrum / Senior Vice President Regulatory Affairs 299 South Main Street, Suite 1700 Salt Lake City, Utah 84111

Serial No.15-387 Docket No. 50-338,339,280,281 10 CFR 71.95(a)(3) Report ATTACHMENT Dominion Shipments Usinq the 8-120B Cask North Anna and Surry Power Stations Dominion

Serial No.15-387 Docket Nos. 50-338,339,280,281 10 CFR 71.95(a)(3) Report Attachment List of Dominion Shipments Using the EnergySolutions 8-120B Cask Station Destination Date of Shipment NAPS Studvic Processing Facility /Erwin, TN 04/02/20 14 NAPS Studvic Processing Facility /Erwin, TN 11/12/2014 NAPS Erwin Resin Solution / Erwin, TN 03/04/2015 SPS Studvic Processing Facility /Erwin, TN 12/04/2013 SPS Studvic Processing Facility/IErwin, TN 03/20/2014 SPS Studvic Processing Facility / Erwin, TN 11/19/2014 SPS Erwin Resin Solution / Erwin, TN 02/25/2015