NRR E-mail Capture - Acceptance Review for Braidwood/Byron Relief Request Regarding Alternative Requirements for the Repair of Reactor Vessel Head Penetrations
ML15077A016
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 03/18/2015
From: Joel Wiebe
Plant Licensing Branch III
To: Krejcie J
Exelon Corp
References
Download: ML15077A016 (2)


Text

NRR-PMDAPEm Resource From: Wiebe, Joel Sent: Wednesday, March 18, 2015 8:12 AM To: Jessica Krejcie

Subject:

Acceptance Review for Braidwood/Byron Relief Request Regarding Alternative Requirements for the Repair of Reactor Vessel Head Penetrations

Jessica, By letter dated September 8, 2014 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML14251A536), Exelon Generation Company, LLC (Exelon), submitted a relief request for Braidwood Station, Units 1 and 2 and Byron Station, Units 1 and 2. The request proposes relaxation of PT examination frequency for installed repairs that have demonstrated continued satisfactory PT examination results. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me at (301) 415-6606.

Joel S. Wiebe, Sr. Project Manager 1

Hearing Identifier: NRR_PMDA Email Number: 1940 Mail Envelope Properties (1A97AE0578A58B46BC77AA0B5DBD720201249964B579)

Subject:

Acceptance Review for Braidwood/Byron Relief Request Regarding Alternative Requirements for the Repair of Reactor Vessel Head Penetrations Sent Date: 3/18/2015 8:11:57 AM Received Date: 3/18/2015 8:11:00 AM From: Wiebe, Joel Created By: Joel.Wiebe@nrc.gov Recipients:

"Jessica Krejcie" <Jessica.Krejcie@exeloncorp.com>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1833 3/18/2015 8:11:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: