Hiowe, Allen From:
Howe, Allen \\ Y(CY-Sent:
Friday, September 16, 2011 3:31 PM To:
Khanna, Meena
Subject:
FW: interview request More pressure Original Message -----
From: Burnell, Scott Sent: Friday, September 16, 2011 2:58 PM To: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM:
Subject:
RE: interview request Hey Brian; Still checking with them -- they're tough to track down when they're in the middle of dealing with the issue. I'll have something before 5.
Scott From: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM: [bwingfield3@bloomberg.net]
Sent: Friday, September 16, 2011 2:56 PM To: Burnell, Scott
Subject:
RE: interview request just checking in. any luck?
Original Message -----
From: Scott Burnell <Scott.Burnell@nrc.gov>
To: BRIAN WINGFIELD (BLOOMBERG/ NEWSROOM:)
At: 9/16 12:00:55 OK, I'll see what I can get today. Thanks.
From: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM: [bwingfield3@bloomberg.net]
Sent: Friday, September 16, 2011 11:58 AM To: Burnell, Scott
Subject:
RE: interview request Just trying to close it out today, so about 5:00PM Original Message -----
From: Scott Burnell <Scott.Burnell(anrc..ov>
To: BRIAN WINGFIELD (BLOOMBERG/ NEWSROOM:)
At: 9/16 11:57:17 Brian; Having trouble tracking down the latest -- what's your deadline? Thanks.
Scott From: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM: [bwingfield3@bloomberg.net]
Sent: Friday, September 16, 2011 9:23 AM To: Burnell, Scott; Ledford, Joey; Hannah, Roger
Subject:
RE: interview request Sure. A few of my questions:
- 1. Is the NRC satisfied that Dominion's inspections so far are sufficient? Is NRC concerned that Dominion is doing too many visual inspections, particularly regarding spent fuel? How does NRC guarantee that Dominion's inspections are satisfactory?
- 2. Dominion says it will have Unit 1 "physically" ready for re-start by Sept. 22? Is that too ambitious? What is a likely re-start timeframe? (Even a ballpark estimate is OK.)
- 3. From NRC's perspective, what happens in the process after Dominion says the plant is ready to re-start?
(I.e. what needs to happen from a regulatory perspective?)
- 4. Dominion has said North Anna is the "test case" for GI-1 99. Do you agree? How important is the North Anna review to the entire GI-1 99 process? Could the GI-1 99 process delay re-start for North Anna?
- 5. It may take a year or more--please correct me if I'm wrong here--to update seismic risks at nuclear plants as part of the GI-199 process. If that's the case, how does NRC know the seismic analysis at North Anna, which is now ongoing, is going to be sufficient?
- thanks, Brian Original Message -----
From: Scott Burnell <Scott. Burnell(nrc..qov>
To: Joey.Ledfordanrc..qov, Roger.Hannah(@nrc.gov, BRIAN WINGFIELD (BLOOMBERG/ NEWSROOM:)
At: 9/16 8:24:20 Brian; Can you give us a better idea of what you'd like to cover? That'll help us figure out who's best-equipped to answer. Thanks.
Scott Original Message -----
From: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM: fmailto:bwinqfield3(@bloomberq.net]
Sent: Thursday, September 15, 2011 4:49 PM To: Burnell, Scott; Ledford, Joey; Hannah, Roger
Subject:
Re: interview request Thanks.
Roger/Joey: If you can help out at all, I'd be grateful.
- best, Brian 2
I,;-- Otiginal Message -----
From: Scott Burnell <Scott.Burnell(anrc.,qov>
To: Joey.Ledfordcnrc.,ov, Roger.Hannah(Dnrc.qov, BRIAN WINGFIELD (BLOOMBERG/ NEWSROOM:)
At: 9/15 16:48:23 Hi Brian; I've asked Eric and Jack for their availability, but perhaps the folks in Atlanta who are running the North Anna inspection might be a decent alternative? Roger and Joey would be able to help you there. Thanks.
Scott Sent from an NRC Blackberry Scott Burnell Original Message -----
From: BRIAN WINGFIELD, BLOOMBERG/ NEWSROOM: <bwinqfield3(bloomberq.net>
To: Burnell, Scott Sent: Thu Sep 15 16:43:38 2011
Subject:
interview request
- Scott, Would Eric Leeds or Jack Grobe be available for a phone interview tomorrow to talk about NRC review of North Anna and GI-1 99? I'm planning a story for next week and would like to get fresh comment from NRC staff if possible.
My schedule is open tomorrow.
- Thanks, Brian Brian Wingfield Bloomberg News 1399 New York Ave., NW Washington, D.C. 20005 202-654-7318 office 3