Pham, Bo From:
Pham, Bo Sent:
Monday, May 17, 2010 6:09 PM To:
Eccleston, Charles
Subject:
RE: Status - Salem/Hope Creek
- Charles, Can you please provide a more complete picture of the status for me, i.e., where are the rest of the chapters?
I thought chapters 1, 3, 6, and 7 were complete, but I haven't seen any of it. Please put them on the shared drive so I can access them as they progqress. I've been asking for this to make the review process a lot smoother.
Also, looking ahead at the calendar, when are you expecting to get the DSEIS in its entirety?
Thanks.
Bo Pham Chief, Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-8450 From: Eccleston, Charles Sent: Monday, May 17, 2010 5:06 PM To: Pham, Bo
Subject:
Status - Salem/Hope Creek Bo here's the status on Salem/Hope Creek.
I've been putting some pressure on AECOM to speed things up. Chapter 2 is nearing completion, it should be ready for delivery to me the end of this week.
Also, AECOM plans to have sections 4.9.2-4.9.5 to me on Friday.
Charles H. Eccleston Nuclear Reactor Regulation Licensing Renewal, Project Manager 301.415.8537 charles.eccleston@nrc.gov 39