UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of AMERENUE (Callaway Plant Unit 2)
AP1000 DESIGN CERTIFICATION AMENDMENT (10 C.F.R. Part 52)
CALVERT CLIFFS NUCLEAR PROJECT, L.L.C.
(Calvert Cliffs Nuclear Power Plant, Unit 3)
DETROIT EDISON CO.
(Fermi Nuclear Power Plant, Unit 3)
DUKE ENERGY CAROLINAS, L.L.C.
(William States Lee III Nuclear Station, Units 1 and 2)
ENERGY NORTHWEST (Columbia Generating Station)
ENTERGY NUCLEAR GENERATION CO. and ENTERGY NUCLEAR OPERATIONS, INC.
(Pilgrim Nuclear Power Station)
ENTERGY NUCLEAR OPERATIONS, INC.
(Indian Point Nuclear Generating Station, Units 2 and 3)
ESBWR DESIGN CERTIFICATION AMENDMENT (10 C.F.R. Part 52)
FIRSTENERGY NUCLEAR OPERATING CO.
(Davis-Besse Nuclear Power Station, Unit 1)
FLORIDA POWER AND LIGHT CO.
(Turkey Point, Units 6 and 7)
LUMINANT GENERATION CO. L.L.C.
(Comanche Peak Nuclear Power Plant, Units 3 and 4)
NEXTERA ENERGY SEABROOK, L.L.C.
(Seabrook Station, Unit 1)
PACIFIC GAS AND ELECTRIC CO.
(Diablo Canyon Power Plant, Units 1 and 2)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket No. 52-037-COL NRC-2010-0131 RIN 3150-A18 Docket No. 52-016-COL Docket No. 52-033-COL Docket Nos. 52-018-COL, 52-019-COL Docket No. 50-397-LR Docket No. 50-293-LR Docket Nos. 50-247-LR, 50-286-LR NRC-2010-0135 RIN-3150-AI85 Docket No. 50-346-LR Docket Nos. 52-040-COL, 52-035-COL Docket Nos. 52-034-COL, 52-035-COL Docket No. 50-443-LR Docket Nos. 50-275-LR, 50-323-LR PPL BELL BEND, L.L.C.
(Bell Bend Nuclear Power Plant)
PROGRESS ENERGY CAROLINAS, INC.
(Shearon Harris Nuclear Power Plant, Units 2 and 3)
PROGRESS ENERGY FLORIDA, INC.
(Levy County Nuclear Power Plant, Units 1 and 2)
SOUTH CAROLINA ELECTRIC AND GAS CO. and SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (also referred to as SANTEE COOPER)
(Virgil C. Summer Nuclear Station, Units 1 and 2)
SOUTHERN NUCLEAR OPERATING CO.
(Vogtle Electric Generating Plant, Units 3 and 4)
SOUTH TEXAS PROJECT NUCLEAR OPERATING CO.
(South Texas Project, Units 3 and 4)
TENNESSEE VALLEY AUTHORITY (Bellefonte Nuclear Power Plant, Units 3 and 4)
TENNESSEE VALLEY AUTHORITY (Watts Bar, Unit 2)
VIRGINIA ELECTRIC AND POWER CO.
d/b/a DOMINION VIRGINIA POWER and OLD DOMINION ELECTRIC COOPERATIVE (North Anna, Unit 3)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket No. 52-039-COL Docket Nos. 52-022-COL, 52-023-COL Docket Nos. 52-029-COL, 52-030-COL Docket Nos. 52-027-COL, 52-028-COL Docket Nos. 52-025-COL, 52-026-COL Docket Nos. 52-012-COL, 52-013-COL Docket Nos. 52-014-COL, 52-015-COL Docket No. 50-391-OL Docket No. 52-017-COL ORDER The Commission is in receipt of a petition to suspend adjudicatory, licensing, and rulemaking activities, and requesting other relief, in the captioned matters.1 This order is to set a schedule for further briefing. Any supplements to the petition may be filed no later than 1 See generally Emergency Petition to Suspend All Pending Reactor Licensing Decisions and Related Rulemaking Decisions Pending Investigation of Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident (served in various dockets between April 14, and April 18, 2011) (Petition). The Commission received a corrected petition on April 18, 2011.
Thursday, April 21, 2011.2 Any person may file an answer to the petition, or a brief amicus curiae, no later than Monday, May 2, 2011.
This order is issued pursuant to my authority under 10 C.F.R. §§ 2.346 (a) and (j).
For the Commission (NRC SEAL)
/RA/
Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 19th day of April, 2011 2 See, e.g., Petition at 4 n.2.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of
)
)
ENERGY NORTHWEST
)
DOCKET NO. 50-397-LR (Columbia Generating Station)
)
)
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Scheduling Order of the Secretary (regarding petitions to suspend adjudicatory, licensing and rulemaking activities), dated April 19, 2011, have been served upon the following persons by Electronic Information Exchange.
U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555-0001 Beth Mizuno, Esq.
beth.mizuno@nrc.gov Brian Newell, Paralegal brian.newell@nrc.gov Lloyd Subin, Esq.
lloyd.subin@nrc.gov Edward Williamson, Esq.
edward.williamson@nrc.gov OGC Mail Center OGCMailCenter@nrc.gov U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Mail Stop: O-16C1 Washington, DC 20555-0001 ocaamail@nrc.gov U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission Mail Stop: O-16C1 Washington, DC 20555-0001 hearingdocket@nrc.gov Applicant Energy Northwest P.O. Box 968, MD PE13 Richland, WA 99352 Pamela Bradley, Assistant General Counsel prbradley@energy-northwest.com Counsel for Applicant Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, N.W.
Washington, DC 20004 Raphael P. Kuyler, Esq.
rkuyler@morganlewis.com Kathryn M. Sutton, Esq.
ksutton@morganlewis.com Petitioner Northwest Environmental Advocates P.O. Box 12187 Portland, OR 972112 Nina Bell, Executive Director nbell@advocates-nwea.org
[Original signed by Linda D. Lewis]
Office of the Secretary of the Commission Dated at Rockville, Maryland this 19th day of April 2011