MONTHYEARML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML21340A2452021-12-0909 December 2021 Exemption from Specific Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0053 (COVID-19)) NRC-21-0057, Work Hour Limits Exemption Request Due to COVID-192021-12-0606 December 2021 Work Hour Limits Exemption Request Due to COVID-19 NRC-21-0036, DTE Electric Company - Request for Exemption from 10 CFR 72.44(d)(3) for Fermi 22021-07-27027 July 2021 DTE Electric Company - Request for Exemption from 10 CFR 72.44(d)(3) for Fermi 2 ML21159A0542021-06-17017 June 2021 Temporary Exemption from Biennial Emergency Preparedness Exercise Frequency Requirements of 10 CFR Part 50, Appendix E, Sections IV.F.2.B and IV.F.2.C (EPID L-2021-LLE-0029 (COVID-19) NRC-21-0031, Request for Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic2021-05-17017 May 2021 Request for Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic ML21109A3742021-04-22022 April 2021 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2021-LLE-0025 (COVID-19)) NRC-21-0027, Work Hour Limits Exemption Request Due to COVID-192021-04-19019 April 2021 Work Hour Limits Exemption Request Due to COVID-19 ML21005A4212021-01-13013 January 2021 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2021-LLE-0002 (COVID-19)) ML21004A1952021-01-0404 January 2021 Work Hour Limits Exemption Request Due to COVID-19 - Supplement ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20343A3502020-12-18018 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(l)(1) (EPID L-2020-LLE-0204 (COVID-19)) ML20332A1792020-12-0808 December 2020 Temporary Exemption from Biennial Emergency Preparedness Exercise Frequency Requirements of 10 CFR Part 50, Appendix E, Sections IV.F.2.B and IV.F.2.C (EPID L-2020-LLE-0188 (COVID-19)) ML20317A2722020-11-18018 November 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0187 (COVID-19)) NRC-20-0071, Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency2020-11-13013 November 2020 Request for Exemption from the Annual Force on Force Training Requirements of 10 CFR 73, Appendix B, Section VI, Due to the COVID-19 Public Health Emergency NRC-20-0070, Work Hour Limits Exemption Request Due to COVID-192020-11-10010 November 2020 Work Hour Limits Exemption Request Due to COVID-19 ML20226A1162020-09-11011 September 2020 Temporary Exemption from the Annual Force-on-Force Training Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI (EPID L-2020-LLE-0128) (COVID-19) ML20192A1802020-07-14014 July 2020 Extension of Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0109 (COVID-19)) NRC-20-0049, Work Hour Limits Exemption Request Due to COVID-19 Revised Second Supplement2020-07-11011 July 2020 Work Hour Limits Exemption Request Due to COVID-19 Revised Second Supplement NRC-20-0048, Work Hour Limits Exemption Request Due to COVID-19 Second Supplement2020-07-10010 July 2020 Work Hour Limits Exemption Request Due to COVID-19 Second Supplement NRC-20-0045, Work Hour Limits Exemption Request Due to COVID-19 Supplement2020-07-0606 July 2020 Work Hour Limits Exemption Request Due to COVID-19 Supplement ML20133K0552020-05-14014 May 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0056 (COVID-19)) ML1112903592011-05-23023 May 2011 Scheduler Exemption from Certain Requirements of 10 CFR Part 73, Section 73.55 NRC-2010-0388, Fed Notice - Fermi 2 Exemption Notice2010-12-27027 December 2010 Fed Notice - Fermi 2 Exemption Notice ML1034303952010-12-27027 December 2010 Exemption from the Requirement of 10 CFR Part 50, Appendix E, Section IV.F.2.b ML1034304212010-12-27027 December 2010 Fed Notice - Fermi 2 Exemption Notice ML1003502252010-03-19019 March 2010 Scheduler Exemption from Certain Requirements of 10 CFR Part 73, Section 73.55 ML0731104822007-12-17017 December 2007 Exemption from the Requirements of 10 CFR 74.19(c) Regarding the Frequency of Physical Inventory of Special Nuclear Material in the Spent Fuel Pool, TAC MD5416 2024-03-20
[Table view] Category:Federal Register Notice
MONTHYEARML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML24086A4312024-04-0505 April 2024 Monthly (28-day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: April 16, 2024 ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML23272A1562023-10-0505 October 2023 Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) FRN ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML22004A2302022-01-20020 January 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in December 2021 ML21188A3562021-08-0606 August 2021 FRN - Notice of Issuance of COVID-19 Exemption Issued in June 2021 ML21123A0842021-05-19019 May 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding Various Parts of 10 CFR Issued in April 2021 ML21028A0122021-02-18018 February 2021 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for January 2021 ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML19140A4562019-05-28028 May 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 06/04/2019 ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 NRC-2017-0238, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 20182017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML17353A1922017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML16270A5552016-12-15015 December 2016 FRN for Issuance of Renewed Operating License for Fermi, Unit 2 ML16244A0972016-09-21021 September 2016 FRN: License Renewal Application for Fermi 2 Nuclear Power Plant ML16145A2252016-06-0707 June 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 2016 NRC-2016-0107, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 20162016-06-0707 June 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: June 7, 2016 ML16033A0792016-02-0303 February 2016 Federal Register Notice Regarding the ACRS Plant License Renewal Subcommittee Meeting, March 2, 2016 (Fermi) ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 ML15295A1742015-10-29029 October 2015 FRN for Fermi 2 Draft SEIS ML15204A2792015-07-27027 July 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 4, 2015 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 NRC-2015-0009, G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units2015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14335A6302015-01-15015 January 2015 G20110262 - Final Response to Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14335A6482015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14303A3812014-10-31031 October 2014 Biweekly Sholly FRN - Application and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: November 12, 2014 ML14161A0162014-06-20020 June 2014 Nuclear Regulatory Commission: (Docket No. 50-341; NRC-2014-0109) DTE Electric Company; Fermi, Unit 2 (FRN) ML14150A3402014-06-11011 June 2014 FRN Acceptability and Opportunity Request Hearing Enclosure 2 with OGC Comments Rev 1 ML14098A2842014-05-0505 May 2014 License Renewal Application; Notice of Receipt and Availability ML14051A6712014-03-0404 March 2014 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: March 4, 2014 NRC-2014-0037, FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: March 4, 20142014-03-0404 March 2014 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: March 4, 2014 ML14037A4142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 NRC-2014-0028, Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 20142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit NRC-2012-0069, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark Ii Containments2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark Ii Containments NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12056A0432012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark II Containments ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status NRC-2011-0230, FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations2011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations ML1126504892011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations NRC-2011-0216, September 20, 2011 Applications and Amendments to Facility Operating License Involving No Significant Hazards Considerations2011-09-0808 September 2011 September 20, 2011 Applications and Amendments to Facility Operating License Involving No Significant Hazards Considerations ML11251A0092011-09-0808 September 2011 September 20, 2011 Applications and Amendments to Facility Operating License Involving No Significant Hazards Considerations NRC-2011-0215, Fermi - Environmental Assessment Fr Notice2011-09-0606 September 2011 Fermi - Environmental Assessment Fr Notice ML1123108752011-09-0606 September 2011 Environmental Assessment and Finding of No Significant Impact ML1123109182011-09-0606 September 2011 Environmental Assessment Fr Notice ML1122302752011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 NRC-2011-0187, Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/20112011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 ML1112903592011-05-23023 May 2011 Scheduler Exemption from Certain Requirements of 10 CFR Part 73, Section 73.55 ML1121606572010-12-31031 December 2010 Attachment I: Pud No 1 V. Wdoe 2024-05-03
[Table view] Category:Letter
MONTHYEARIR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 19, 2010 Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166 SUB"IECT: FERMI 2 - SCHEDULER EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 73, SECTION 73.55 (TAC NO. ME2656)
Dear Mr. Davis:
The Commission has approved the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR), Part 73 for Fermi 2. This action is in response to your application dated November 19, 2009, as supplemented by letter dated December 23, 2009, that requested an extension of the deadline from March 31, 2010, until May 31, 2011, for the implementation of certain measures in 10 CFR Part 73, as revised on March 27, 2009.
A copy of the exemption is enclosed. The exemption has been forwarded to the Office of the Federal Register for publication.
Sincerely, Mahesh Chawla, Project Manager Plant Licensing Branch "1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Exemption cc w/encl: Distribution via Listserv
7590-01-P UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION DETROIT EDISON COMPANY FERMI 2 DOCKET NO. 50-341 EXEMPTION
1.0 BACKGROUND
Detroit Edison Company (the licensee) is the holder of Facility Operating License No. NPF-43, which authorizes operation of Fermi 2. The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the U.S. Nuclear Regulatory Commission (NRC, the Commission) now or hereafter in effect.
The facility consists of one boiling-water reactor located in Monroe County, Michigan.
2.0 REQUEST/ACTION Title 10 of the Code of Federal Regulations (10 CFR) Part 73, "Physical protection of plants and materials," Section 73.55, "Requirements for physical protection of licensed activities in nuclear power reactors against radiological sabotage," published March 27, 2009, effective May 26,2009, with a full implementation date of March 31,2010, requires licensees to protect, with high assurance, against radiological sabotage by designing and implementing comprehensive site security programs. The amendments to 10 CFR 73.55 published on March 27,2009, establish and update generically applicable security requirements similar to those previously imposed by Commission orders issued after the terrorist attacks of September 11,2001, and implemented by licensees. In addition, the amendments to 10 CFR 73.55 include additional requirements to further enhance site security based upon insights gained from implementation of the post-September 11, 2001, security orders. It is from
-2 five of these new requirements that Fermi 2 now seeks an exemption from the March 31, 2010, implementation date. All other physical security requirements established by this recent rulemaking have already been or will be implemented by the licensee by March 31,2010.
By letter dated November 19, 2009, as supplemented by letter dated December 23, 2009, the licensee requested an exemption in accordance with 10 CFR 73.5, "Specific exemptions." The licensee's November 19, 2009, and December 23, 2009, letters, have certain portions which contain proprietary and safeguards information and, accordingly, are not available to the public. The licensee has requested an exemption from the March 31, 2010, compliance date stating that it must complete a number of significant modifications to the current site security configuration before all requirements can be met. Specifically, the request is to extend the compliance date for five requirements that would be in place by May 31,2011, versus the March 31, 2010, deadline. Being granted this exemption for the five requirements would allow the licensee to complete the modifications designed to update qging equipment and incorporate state-of-the-art technology to meet or exceed the noted regulatory requirements.
3.0 DISCUSSION OF PART 73 SCHEDULE EXEMPTIONS FROM THE MARCH 31, 2010, FULL IMPLEMENTATION DATE Pursuant to 10 CFR 73.55(a)(1), "By March 31, 2010, each nuclear power reactor licensee, licensed under 10 CFR Part 50, shall implement the requirements of this section through its Commission-approved Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Cyber Security Plan referred to collectively hereafter as
'security plans.'" Pursuant to 10 CFR 73.5, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 73 when the exemptions are authorized by law, and will not endanger life or property or the common defense and security, and are otherwise in the public interest.
-3 NRC approval of exemption, as noted above, would allow an extension from March 31, 2010, to May 31,2011, for the implementation date for five specified areas of the new rule. The NRC staff has determined that granting of the licensee's proposed exemption would not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commission's regulations.
Therefore, the exemption is authorized by law.
In the draft final power reactor security rule provided to the Commission, the NRC staff proposed that the requirements of the new regulation be met within 180 days. The Commission directed a change from 180 days to approximately 1 year for licensees to fully implement the new requirements. This change was incorporated into the final rule. From this, it is clear that the Commission wanted to provide a reasonable timeframe for licensees to achieve full compliance.
As noted in the final rule, the Commission also anticipated that licensees would have to conduct site-specific analyses to determine what changes were necessary to implement the rule's requirements, and that any such changes could be accomplished through a variety of licensing mechanisms, including exemptions. Since issuance of the final rule, the Commission has rejected a generic industry request to extend the rule's compliance date for all operating nuclear power plants, but noted that the Commission's regulations provide mechanisms for individual licensees, with good cause, to apply for relief from the compliance date (
Reference:
June 4,2009, letter, from R. W. Borchardt, NRC, to M. S. Fertel, Nuclear Energy Institute). The licensee's request for an exemption is therefore consistent with the approach set forth by the Commission and discussed in the June 4, 2009, letter.
Fermi 2 Schedule Exemption Request The licensee provided detailed information in Enclosures 1 and 2 of its supplemental submittal to its November 19, 2009, letter, requesting an exemption. It describes a comprehensive plan which provides a timeline for achieving full compliance with the new
-4 regulation. Enclosures 1 and 2 contain proprietary information regarding the site security plan, details of the specific requirements of the regulation for which the site cannot be in compliance by the March 31, 2010, deadline and why, the required changes to the site's security configuration, and a timeline with "critical path" activities that will enable the licensee to achieve full compliance by May 31, 2011. The timeline provides dates indicating when (1) construction will begin on various phases of the project (Le., new buildinqs and fences), and (2) critical equipment will be installed, tested and become operational.
Notwithstanding the schedule exemptions of these limited requirements, the licensee indicated that it will continue to be in compliance with all other applicable physical security requirements as described in 10 CFR 73.55 and reflected in its current NRC-approved physical security program. By May 31, 2011, the licensee also stated that Fermi 2 will be in full compliance with the regulatory requirements of 10 CFR 73.55, as issued on March 27, 2009.
4.0 CONCLUSION
FOR PART 73 SCHEDULE EXEMPTION REQUEST The NRC staff has reviewed the licensee's submittals and concludes that the licensee has provided adequate justification for its request for an extension of the compliance date to May 31, 2011, with regard to five specified requirements of 10 CFR 73.55.
Accordingly, the Commission has determined that pursuant to 10 CFR 73.5, "Specific exemptions," an exemption from the March 31, 2010, compliance date is authorized by law and will not endanger life or property or the common defense and security, and is otherwise in the public interest. Therefore, the Commission hereby grants the requested exemption. The NRC staff has determined that the long-term benefits that will be realized when the Fermi 2 modifications are completed justifies exceeding the full compliance date in the case of this particular licensee. The security measures Fermi 2 needs additional time to implement are new requirements imposed by March 27, 2009, amendments to 10 CFR 73.55, and are in addition to those currently required by the security orders issued in response to the events of
-5 September 11, 2001. Therefore, the NRC concludes that the licensee's actions are in the best interest of protecting the public health and safety through the security changes that will result from granting this exemption.
As per the licensee's request and the NRC's regulatory authority to grant an exemption from the March 31, 2010, deadline for the five requirements specified in Enclosure 1 of the Detroit Edison letter dated December 23, 2009, the licensee is required to be in full compliance by May 31, 2011. In achieving compliance, the licensee is reminded that it is responsible for determining the appropriate licensing mechanism (i.e., 10 CFR 50.54(p) or 10 CFR 50.90) for incorporation of all necessary changes to its security plans.
Pursuant to 10 CFR 51.32, "Finding of no significant impact," the Commission has previously determined that the granting of this exemption will not have a significant effect on the quality of the human environment [75 FR 11946; dated March 12, 2010].
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 19t1}jay of March 2010.
FOR THE NUCLEAR REGULATORY COMMISSION Ii cZt~p(~~
Allen G. Howe, Acting Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
LTR: ML100350225 Exemption FRN: ML100350146 OFFICE DORLlLPL3-1/PM DORLlLPL3-1/LA DORULPL3-1/BC NSIR/DSP/RSLRLB/BC NAME MChawla BTuily RPascarelli DHuyck w/comments DATE 03/03/10 03/03/10 03/19/10 03/03/10 OFFICE NSIR/DSP/D OGC NRR/DORLlActing Director NAME SMorris w/several comments AJones NLO AHowe DATE 03/03/10 03/16/10 03/19/10