ML093480229

From kanterella
Jump to navigation Jump to search
Tennessee Valley Authoritys Brief in Opposition to Sierra Club, ET Al. Appeal from LBP-09-26
ML093480229
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 12/14/2009
From: Sutton K, Vigluicci E
Morgan, Morgan, Lewis & Bockius, LLP, Tennessee Valley Authority
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-391-OL, ASLBP 09-893-01-OL-BD01, LBP-09-26, RAS 16827
Download: ML093480229 (13)


Text

DB1/64073193.1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION

)

In the Matter of

)

)

Docket No. 50-391-OL TENNESSEE VALLEY AUTHORITY

)

)

December 14, 2009 (Watts Bar Nuclear Plant Unit 2)

)

)

TENNESSEE VALLEY AUTHORITYS BRIEF IN OPPOSITION TO SIERRA CLUB, ET AL. APPEAL FROM LBP-09-26 I.

INTRODUCTION In accordance with 10 C.F.R. § 2.311(b), Tennessee Valley Authority (TVA) submits this Brief in Opposition to the Notice of Appeal and Brief on Appeal (Appeal) filed by the Sierra Club, Blue Ridge Environmental Defense League, Tennessee Environmental Counsel, and We the People, Inc. (collectively, Petitioners), regarding the November 19, 2009 Order issued by the Atomic Safety and Licensing Board (Board) (Order or LBP-09-26).1 Unlike the other participant in this proceeding, Southern Alliance for Clean Energy (SACE), Petitioners did not seek and were not granted an extension of the June 30, 2009 deadline for filing petitions to intervene.2 Nonetheless, on July 13, 2009, Petitioners and SACE filed a joint Petition to 1

Notice of Appeal of LBP-09-26 by Sierra Club, Blue Mountain Environmental Defense League, Tennessee Environmental Council, and We the People, Inc. (Dec. 3, 2009); Brief on Appeal of LBP-26-09 [sic] by Sierra Club, Blue Mountain Environmental Defense League, Tennessee Environmental Council, and We the People, Inc. (Dec. 3, 2009) (Appeal). Although the Appeal and certain other pleadings refer to the Blue Mountain Environmental Defense League, the Petition to Intervene and Request for Hearing (July 13, 2009) (Petition to Intervene) and Board Order refer to the Blue Ridge Environmental Defense League. TVA assumes that this difference is due to a typographical error.

2 See Notice of Receipt of Update to Application for Facility Operating License and Notice of Opportunity for Hearing for the Watts Bar Nuclear Plant, Unit 2 and Order Imposing Procedures for Access to Sensitive

2 Intervene and Request for Hearing. More than a month laterand only after TVA and NRC Staff raised the lateness issuePetitioners asked the Board to accept their untimely filing, explaining that the failure to seek an extension of the June 30th deadline was due to their own indecision regarding intervention, coupled with inattention of counsel.3 The Board denied Petitioners request, and Petitioners appealed the Board decision, asking the Commission to find that the Board abused its discretion, describing the Boards Order as irrational, unfair, illogical, and not following common sense.4 As discussed more fully below, the Board properly denied Petitioners request because they did not submit a timely Petition to Intervene and failed to provide adequate justification to allow the Board to consider their non-timely filing pursuant to the 10 C.F.R. § 2.309(c)(1) factors. Accordingly, the Commission should affirm the Boards decision and find that failure to meet a deadline due to indecision or inattention is not an adequate basis for missing an acknowledged, published filing deadline.

II.

PROCEDURAL HISTORY The Commission published the Hearing Notice for this operating license proceeding in the Federal Register on May 1, 2009, setting a clear, firm deadline of June 30, 2009 for filing any request for hearing and petition to intervene.5 On June 16, 2009, SACE filed a Request for Extension of Time to Submit Hearing Request/Petition to Intervene, seeking a two-week Unclassified Non-Safeguards Information and Safeguards Information for Contention Preparation, 74 Fed.

Reg. 20,350, 20,350-51 (May 1, 2009) (Hearing Notice).

3 Motion to Permit Late Addition of Co-Petitioners to Southern Alliance for Clean Energys Petition to Intervene and Admit Them as Intervenors at 1-3 (Aug. 14, 2009) (Motion to Permit Late Addition of Petitioners).

4 Appeal at 5-8.

5 Hearing Notice, 74 Fed. Reg. at 20,350-51. In order to ensure adequate notice, NRCs Hearing Notice also specifically provided that... the notice of the application will be published once each week for 4 consecutive weeks in the Federal Register, but that the 60-day period will only begin upon the date of the first publication of the notice. Hearing Notice at 20,351.

3 extension of time (SACEs Request for Extension of Time).6 Importantly, SACEs Request for Extension of Time made no mention of Petitioners and explicitly applied only to SACE.

TVA timely filed its response to SACEs Request for Extension of Time, wherein it agreed to SACEs request and noted that it had offered to provide SACE with any requested information and documents in a timely manner.7 TVA did not agree to any request for extension for any parties other than SACE. On June 24, 2009, the Secretary of the Commission granted SACE until July 14th to file a request for hearing and petition to intervene.8 This Order applied specifically to SACE and did not impact the filing deadline for any other potential parties. On July 13, 2009, SACE, joined by Petitioners, filed a Petition to Intervene and Request for Hearing.

The Petition to Intervene contained no discussion of the fact that the filing was not timely with respect to the Petitioners.

On August 7, 2009, TVA and the NRC Staff filed Answers to the Petition to Intervene, arguing that Petitioners should not be admitted as parties to this proceeding because their filing was impermissibly late.9 In their Reply, Petitioners candidly acknowledged that the Secretarys June 24th Order granted only SACE an extension and, thus, the Petition to Intervene was untimely with respect to the Petitioners.10 Petitioners also concurrently filed a Motion to Permit Late Addition of Petitioners. In this Motion, Petitionersfor the first time and thirty-two days lateclaimed to satisfy the late-filing factors in 10 C.F.R. § 2.309(c)(1). On August 21, 2009, 6

SACE cited difficulties in accessing certain documents SACE needed to prepare its contentions and also scheduling conflicts of two of SACEs experts. See SACEs Request for Extension of Time at 1-2.

7 See Response of the Tennessee Valley Authority to Request for Extension of Time to Submit Hearing Request/Petition to Intervene by Southern Alliance for Clean Energy (June 18, 2009).

8 Order (June 24, 2009) (unpublished) (June 24th Order).

9 See Tennessee Valley Authoritys Answer Opposing the Southern Alliance for Clean Energy, et al., Petition to Intervene and Request for Hearing at 2, 16-18 (Aug. 7, 2009); NRC Staffs Answer to Petition to Intervene and Request for Hearing at 13 (Aug. 7, 2009).

10 Petitioners Reply to NRC Staffs and Tennessee Valley Authoritys Answers to Petition to Intervene and Request for Hearing at 2 (Aug. 14, 2009) (Reply).

4 TVA and the NRC Staff filed responses to the Motion to Permit Late Addition of Petitioners explaining that the Motion itself was untimely and that, in any event, Petitioners failed to carry their burden of showing that the late-filing factors in Section 2.309(c)(1) weighed in their favor.11 In its November 19th Order, the Board granted SACEs timely Petition to Intervene, but denied Petitioners belated request, finding that Petitioners filing was not timely and failed to provide adequate justification.12 On December 3, 2009, Petitioners appealed LBP-09-26 to the Commission. TVA hereby opposes Petitioners Appeal.

III.

STANDARD OF REVIEW An order denying a petition to intervene, and/or request for hearing... is appealable by the requestor/petitioner on the question as to whether the request and/or petition should have been granted.13 In ruling on such an appeal, however, the Commission gives substantial deference to Board determinations on threshold issues.14 Thus, a Boards decision ruling on a non-timely petition will be reversed only if there was an abuse of discretion or error of law.15 Abuse of discretion is a high standard of review.16 A petitioner has a heavy burden on appeal to establish that reversal of a Board decision is warranted.17 Furthermore, consistent with this standard, [t]he appellant bears the responsibility of clearly identifying the errors in the 11 Tennessee Valley Authoritys Answer Opposing the Motion to Permit Late Addition of Co-Petitioners to Southern Alliance for Clean Energys Petition to Intervene and Admit Them as Intervenors (Aug. 21, 2009);

NRC Staffs Response in Opposition to Motion to Permit Late Addition of Co-Petitioners (Aug. 21, 2009).

12 Tenn. Valley Authority (Watts Bar Nuclear Plant), LBP-09-26, 70 NRC __, slip op. at 2-3, 6-9, 63 (Nov. 19, 2009).

13 10 C.F.R. § 2.311(c).

14 AmerGen Energy Co., LLC (License Renewal for Oyster Creek Nuclear Generating Station), CLI-06-24, 64 NRC 111, 121 (2006).

15 Private Fuel Storage, LLC (Independent Spent Fuel Storage Installation), CLI-00-21, 52 NRC 261, 265 (2000).

16 Andrew Siemaszko, CLI-06-16, 63 NRC 708, 718 (2006).

17 Pub. Serv. Co. of N.H. (Seabrook Station, Units 1 & 2), ALAB-918, 29 NRC 473, 482 (1989).

5 decision below and ensuring that its brief contains sufficient information and cogent argument to alert the other parties and the Commission to the precise nature of and support for the appellants claims.18 In performing its appellate review role, the Commission will not consider new arguments that were never presented to the Board.19 Raising new issues on appeal is especially inappropriate when the issue and the factual averments underlying it could have beenbut were nottimely put before the Licensing Board.20 IV.

PETITIONERS HAVE IDENTIFIED NO ERROR OF LAW OR ABUSE OF DISCRETION IN THE BOARDS ORDER As an initial matter, Petitioners concede that their Petition to Intervene was untimely and, thus, may not be considered unless it satisfies the eight-factor balancing test for non-timely filings set forth in 10 C.F.R. § 2.309(c)(1).21 The burden is on a petitioner to demonstrate that a balancing of these factors weighs in its favor.22 Importantly, the eight factors in Section 2.309(c)(1) are not of equal importanceabsence of good cause (factor one) is the first 18 Dominion Nuclear Power Conn. Inc. (Millstone Nuclear Power Station, Units 2 & 3), CLI-04-36, 60 NRC 631, 639 n.25 (2004) (quoting Advanced Med. Sys., Inc. (One Factory Row, Geneva, Ohio 44041), CLI-94-6, 39 NRC 285, 297 (1994)).

19 USEC, Inc. (American Centrifuge Plant), CLI-06-10, 63 NRC 451, 458 (2006); Millstone, CLI-04-36, 60 NRC at 640.

20 P.R. Elec. Power Auth. (Northern Coast Nuclear Plant, Unit 1), ALAB-648, 14 NRC 34, 37 (1981).

21 See Reply at 2 (Petitioners agree that... their request to participate in this proceeding is untimely.).

The eight factors in Section 2.309(c)(1) are: (1) good cause, if any, for the failure to file on time; (2) the nature of the requestors/petitioners right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestors/petitioners property, financial or other interest in the proceeding; (4) the possible effect of any order that may be entered in the proceeding on the requestors/petitioners interest; (5) the availability of other means whereby the requestors/petitioners interest will be protected; (6) the extent to which the requestors/petitioners interests will be represented by existing parties; (7) the extent to which the requestors/petitioners participation will broaden the issues or delay the proceeding; and (8) the extent to which the requestors/petitioners participation may reasonably be expected to assist in developing a sound record.

22 Tex. Utils. Elec. Co. (Comanche Peak Steam Electric Station, Units 1 & 2), CLI-88-12, 28 NRC 605, 609 (1988), affd sub nom. Citizens for Fair Util. Regulation v. NRC, 898 F.2d 51 (5th Cir. 1990). In fact, the Commission has summarily rejected petitions that fail to address the non-timely filing factors. See, e.g., Fla.

Power & Light Co. (Calvert Cliffs Nuclear Plant, Units 1 & 2), CLI-06-21, 64 NRC 30, 33-34 (2006).

6 and principal test.23 Absent a favorable showing on the good cause factor, a petitioner must show a compelling case on the remaining factors.24 Of the remaining factors, the potential for broadening or delaying the proceeding (factor seven) and the petitioners ability to assist in developing a sound record (factor eight), are the most important factors.25 To make a compelling showing on factor eight, a petitioner must provide specific details regarding the issues it plans to cover and the witnesses and testimony it plans on presenting.26 As explained more fully below, Petitioners fail to demonstrate any abuse of discretion or legal error in the Boards decision.

A.

The Board Did Not Abuse its Discretion in Finding Petitioners Failed to Demonstrate Good Cause for Their Failure to File on Time The Board properly found that Petitioners failed to demonstrate good cause. As the Board explained, Petitioners candidly state that they did not join SACE in seeking an extension because at the time the extension was requested they had not yet decided whether to join SACE in the Petition to Intervene. Such indecision does not constitute good cause for failure to file a timely petition.27 On appeal, Petitioners generally claim that the Boards decision was irrational, unfair, illogical, and does not follow common sense simply because, if SACE had good cause for its two-week extension, then Petitioners also must have good cause for a two-week extension.28 23 State of New Jersey (Dept of Law & Pub. Safetys Requests Dated Oct. 8, 1993), CLI-93-25, 38 NRC 289, 295 (1993) (citing Duke Power Co. (Catawba Nuclear Station, Units 1 & 2), CLI-83-19, 17 NRC 1041, 1048 (1983)).

24 Id. at 296; see also Tex. Utils. Elec. Co. (Comanche Peak Steam Electric Station, Units 1 & 2), CLI-92-12, 36 NRC 62, 73 (1992) (holding that when no good excuse is tendered for the tardiness, the petitioners demonstration on the other factors must be particularly strong) (citation and internal punctuations omitted).

25 Commonwealth Edison Co. (Braidwood Nuclear Power Station, Units 1 & 2), CLI-86-8, 23 NRC 241, 246-48 (1986).

26 Comanche Peak, CLI-88-12, 28 NRC at 611 (quoting Miss. Power & Light Co. (Grand Gulf Nuclear Station, Units 1 & 2), ALAB-704, 16 NRC 1725, 1730 (1982)).

27 Watts Bar, LBP-09-26, slip op. at 8.

28 Appeal at 5-8.

7 As demonstrated by their reasoning, Petitioners still have not come to grips with the fact that, unlike SACE, they did not seek and were not granted an extension of time to file their Petition to Intervene. Although Petitioners do not indicate when they decided to join SACE in its Petition to Intervene, thirty-two days passed between the filing of the Petition to Intervene and Petitioners first attempt to address the late-filing factors. Given this prolonged period of inaction by Petitioners, the Board properly focused its good cause analysis on why Petitioners did not join in SACEs extension request or, at a minimum, submit a timely Motion to Permit Late Addition of Petitioners.29 Petitioners only explanation for this delay was that they had not yet decided to join SACE in the Petition to Intervene and then their counsel overlooked this requirement.30 Thus, the Board decision was proper because ambivalence regarding intervention, coupled with the acknowledged error of experienced counsel, does not constitute good cause.31 Accordingly, there is no abuse of discretion in the Board finding an absence of good cause.

B.

The Board Committed No Legal Error in Requiring That Petitioners Make a Compelling Showing on the Remaining Factors and Did Not Abuse Its Discretion in Finding That Petitioners Failed to Make Such a Showing Given that the Board properly concluded that Petitioners failed to establish good cause, the Board appropriately required that Petitioners make a compelling showing on the remaining 29 See, e.g., New Jersey, CLI-93-25, 38 NRC at 295 (explaining that in addressing the good cause factor, a petitioner must explain not only why it failed to file within the time required, but also why it did not file as soon thereafter as possible).

30 Motion to Permit Late Addition of Petitioners at 2.

31 See Calvert Cliffs, CLI-06-21, 64 NRC at 33 ([w]e cannot agree that [the petitioners] failure to read carefully the governing procedural regulations constitutes good cause for accepting its late-filed petition) (quoting N.

Atl. Energy Serv. Corp. (Seabrook Station, Unit 1), CLI-99-6, 49 NRC 201, 223 (1999)); Kan. Gas & Elec. Co.

(Wolf Creek Generating Station, Unit No. 1), ALAB-279, 1 NRC 559, 576-77 (1975) (observing that the Commission has given licensing boards leeway in evaluating intervention petitions drafted by pro se petitioners or counsel new to the field, but declining to do so because the petition bears the imprimatur of experienced counsel who could be expected to file a petition with the clarity and specificity demanded by the Commissions regulations).

8 Section 2.309(c)(1) factors. As the Board explained, under the governing Commission case law, when a petitioner fails to make a showing of good cause, the petitioners demonstration on the other factors must be compelling.32 The Board then properly evaluated and weighed those factors, noting that several factors weighed in Petitioners favor, but that on balance, Petitioners showing on the other Section 2.309(c)(1) factors was not so compelling to warrant consideration of Petitioners non-timely filing.33 Specifically, the Board noted that the standing-related factors (factors two to four) and the potential for broadening or delaying the proceeding (factor seven),

weighed in Petitioners favor.34 The Board, however, found Petitioners arguments that SACE might not protect Petitioners interests if SACE withdrew from the proceeding (factor six), and that Petitioners could make a significant contribution to record (factor eight), were largely unsubstantiated.35 On appeal, Petitioners agree that the compelling showing standard is applicable when good cause is not established.36 They claim, however, that the Board committed legal error by requiring a compelling showing on the remaining Section 2.309(c)(1) factors after they established good cause.37 This circular argument is nothing more than a rehash of Petitioners challenge to the Boards finding that good cause was absent. As discussed in Section IV.A above, the Board justifiably found that Petitioners failed to demonstrate good cause and, therefore, the Board correctly required a compelling showing on the remaining factors.

32 Watts Bar, LBP-09-26, slip op. at 6 (quoting Dominion Nuclear Conn. Inc. (Millstone Nuclear Power Station, Units 2 & 3), CLI-05-24, 62 NRC 551, 565 (2005)).

33 Watts Bar, LBP-09-26, slip op. at 8.

34 Id..

35 Id. at 8-9.

36 Appeal at 7.

37 Id..

9 Petitioners next challenge the Boards conclusions on factors six and eight. With respect to the sixth factor (extent to which petitioners interests will be represented by existing parties),

the Board refused to give significant weight to Petitioners hypothetical scenario involving SACEs possible, future withdrawal from the proceeding, finding the claim speculative.38 On appeal, Petitioners claim the Boards conclusion lacks a reasonable basis, but point to no facts or evidence to support this hypothetical.39 This argument also ignores controlling Commission case law holding that the weight given to this factor is only slight and insufficient to satisfy the compelling showing standard.40 Accordingly, the Board did not abuse its discretion in not giving significant weight to Petitioners bare, unsupported hypothetical regarding the potential withdrawal of SACE from the proceeding.41 With regard to the eighth factor (ability to assist in developing a sound record), the Board found that Petitioners failed to explain how their knowledge of these facts is superior to, or even different from, that of SACE or why, if they are not admitted as parties, they could not, nevertheless, provide such services to SACE.42 On appeal, Petitioners simply assert that the Board disregarded Petitioners special knowledge about local economic and environmental 38 Watts Bar, LBP-09-26, slip op. at 8-9.

39 Appeal at 8.

40 Comanche Peak, CLI-92-12, 36 NRC at 74. See also Westinghouse Elec. Corp. (Nuclear Fuel Export License for Czech RepublicTemelin Nuclear Power Plants), CLI-94-7, 39 NRC 322, 329 (1994) (explaining that excusing untimeliness for every petitioner who meets only this factor would effectively negate any standards for untimely intervention in cases... where no one else has requested a hearing, since a late-filing petitioner could always maintain that there will be no hearing to protect its interest).

41 Petitioners original argument on this factor consisted of the following statement: If the Co-Petitioners are not admitted, and if for any reason SACE is later forced to withdraw from this proceeding, no other parties will be left in this proceeding to represent the interests of the Co-Petitioners. Motion to Permit Late Addition of Petitioners at 3. In their Appeal, Petitioners attempt to expand on this argument by stating that, [g]iven the significant demands of any NRC licensing proceeding, and given the length of a typical operating license case, it is not unreasonable to anticipate circumstances in which an intervenor would be forced to drop out of a case for lack of resources. Appeal at 8. Although this argument was never presented to the Board and thus, need not be considered by the Commission, see USEC, CLI-06-10, 63 NRC at 458, such assertions are generally applicable to any proceeding and do not satisfy Petitioners burden to make a compelling showing.

42 Watts Bar, LBP-09-26, slip op. at 9.

10 issues, but again provide no facts or evidence to support or establish any such special knowledge.43 In fact, it appears that the experts in this proceeding were retained by SACE before Petitioners even decided to join the petition.44 Under Commission case law, to make a compelling case on this factor, Petitioners were required to set out with as much particularity as possible the precise issues it plans to cover, identify its prospective witnesses, and summarize their proposed testimony in order to demonstrate their special expertise.45 Beyond vague assertions, Petitioners did not identify any specific issues they planned to address and did not list any additional witness they might call.46 Again, given the complete absence of specific and detailed information regarding Petitioners special knowledge, the Board did not abuse its discretion in not giving significant weight to this factor.

V.

CONCLUSION For the foregoing reasons, the Commission should reject Petitioners Appeal and affirm the Boards Order.

43 Appeal at 8.

44 See SACEs Request for Extension of Time at 2, 5-6 (referring to SACEs expert consultants, Drs. Shawn Young and Arjun Makhijani) (emphasis added).

45 Comanche Peak, CLI-88-12, 28 NRC at 611 (quoting Grand Gulf,, ALAB-704, 16 NRC at 1730).

46 See Motion to Permit Late Addition of Petitioners at 4.

11 Respectfully submitted, Signed (electronically) by Paul M. Bessette Kathryn M. Sutton, Esq.

Paul M. Bessette, Esq.

Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004 Phone: 202-739-3000 Fax: 202-739-3001 E-mail: pbessette@morganlewis.com Edward J. Vigluicci, Esq.

Office of the General Counsel Tennessee Valley Authority 400 W. Summit Hill Drive, WT 6A-K Knoxville, TN 37902 Phone: 865-632-7317 Fax: 865-632-3307 E-mail: ejvigluicci@tva.gov Counsel for TVA Dated in Washington, D.C.

this 14th day of December 2009

DB1/64073193.1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION

)

In the Matter of

)

)

Docket No. 50-391-OL TENNESSEE VALLEY AUTHORITY

)

)

December 14, 2009 (Watts Bar Nuclear Plant Unit 2)

)

)

CERTIFICATE OF SERVICE I hereby certify that, on December 14, 2009, a copy of Tennessee Valley Authoritys Brief in Opposition to Sierra Club, Et al. Appeal from LBP-09-26, was served by the Electronic Information Exchange on the following recipients:

Administrative Judge Lawrence G. McDade, Chair Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, DC 20555-0001 E-mail: lgm1@nrc.gov Administrative Judge Dr. Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, D.C. 20555-0001 E-mail: pba@nrc.gov Administrative Judge Dr. Gary S. Arnold Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, D.C. 20555-0001 E-mail: gxa1@nrc.gov Office of the Secretary U.S. Nuclear Regulatory Commission Rulemakings and Adjudications Staff Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov

2 Edward Williamson, Esq.

David Roth, Esq.

Andrea Jones, Esq.

Jeremy M. Suttenberg, Esq.

Office of the General Counsel U.S. Nuclear Regulatory Commission Mail Stop: O-15D21 Washington, DC 20555-0001 E-mail: elw2@nrc.gov; david.roth@nrc.gov; andrea.jones@nrc.gov; jeremy.suttenberg@nrc.gov Wen Bu, Law Clerk Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop T-3F23 Washington, DC 20555-0001 E-mail: wxb3@nrc.gov Diane Curran, Esq.

Matthew D. Fraser, Esq.

Representative of Southern Alliance for Clean Energy (SACE)

Matthew Harmon, Curran, Spielberg &

Eisenberg, L.L.P.

1726 M Street N.W., Suite 600 Washington, D.C. 20036 E-mail: dcurran@harmoncurran.com; mfraser@harmoncurran.com Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Mail Stop: O-16C1 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Signed (electronically) by Paul M. Bessette Kathryn M. Sutton, Esq.

Paul M. Bessette, Esq.

Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, N.W.

Washington, D.C. 20004 Phone: 202-739-3000 Fax: 202-739-3001 E-mail: pbessette@morganlewis.com