NFPA 805 Pilot License Amendment Request Review

& Infrastructure Update SHEARON HARRIS (Harris) NFPA 805 License Amendment Request Date Available (LAR) REVIEW SCHEDULE (Progress Energy) Information Harris LAR Submittal Letter from Progress Energy with Partial Enclosures 5/29/08 ML081560641 Remaining Harris LAR Enclosures 5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting Summary: Clarification Call on Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement (Part 1) due 11/08 **

Harris LAR Supplement (Part 2) due 12/08 Harris LAR Site Audit (tentative) 2/09*

Issue LAR Request for Additional Information (RAI) to Progress Energy 3/09*

Harris LAR RAI Responses due from Progress Energy 5/09*

Harris Safety Evaluation Issued to Progress Energy 9/09*

OCONEE NFPA 805 LAR REVIEW SCHEDULE (Duke Energy) Date Available Information Oconee LAR Submittal Letter from Duke Energy with Partial Enclosure 5/30/08 ML081650475 Remaining Oconee LAR Enclosures 5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 Oconee LAR Supplement due 10/31/08 **

NRC LAR Acceptance Review Letter to Duke Energy 12/08 Oconee LAR Site Visit (tentative) 2/09*

Issue Oconee LAR RAIs to Duke Energy 3/09*

Oconee LAR RAI Responses due from Duke Energy 5/09*

LAR Safety Evaluation Issued to Duke Energy 9/09*

NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received from the Nuclear Energy Institute (NEI) NEI 00-01, Revision 2 12/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/08 ML081400332 Send NRC Comments on NEI 00-01, Rev 2 5/08 ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection 10/08 ML082830934 Public Meeting Summary NFPA 805 Regulatory Audit Plan Template Memo 12/08 (internal memorandum; will be publicly available in ADAMS)

SRP 9.5.1.2 Published for Public Comment 1/09 Send NRC Comments on NEI 04-02, Rev 2 2/09 (unless covered in RG 1.205, Revision 1)

Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09

  • These milestone dates are estimates based on a high-quality supplemental submittal.