Report 22, Inspection Plan
ML082460548
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 09/02/2008
From:
NRC/RGN-II
To:
Shared Package
ML082460353 List:
References
Download: ML082460548 (2)


Text

Page 1 of 2 McGuire 09/02/2008 11:26:05 Inspection / Activity Plan Report 22 09/01/2008 - 12/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3ISI - UNIT 1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/29/2008 10/03/2008 Baseline Inspections EB3SGISI - UNIT 1 SERVICE GENERATOR INSERVICE INSP 1 1 IP 7111108P Inservice Inspection Activities - PWR 10/06/2008 10/10/2008 Baseline Inspections PSB1-EP - EMERGENCY PREPAREDNESS INSPECTION 1 1, 2 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 10/06/2008 10/10/2008 Baseline Inspections 1, 2 IP 7111402 Alert and Notification System Testing 10/06/2008 10/10/2008 EP Baseline Inspection 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 10/06/2008 10/10/2008 EP Baseline Inspection 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 10/06/2008 10/10/2008 EP Baseline Inspection 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 10/06/2008 10/10/2008 EP Baseline Inspection 1, 2 IP 71151-EP01 Drill/Exercise Performance 10/06/2008 10/10/2008 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 10/06/2008 10/10/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 10/06/2008 10/10/2008 Baseline Inspections TI-171 - B.5.B PHASE 2&3 3 1, 2 IP 2515/171 Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 11/03/2008 11/07/2008 Generic Safety Inspectio TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 6 1, 2 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial] 03/09/2009 03/13/2009 Baseline Inspections 1, 2 IP 7111105P Fire Protection-NFPA 805 Transition Period [Triennial] 03/23/2009 03/27/2009 Baseline Inspections OL EXAM - INITIAL EXAM PREP 4 1 V23306 MCGUIRE/MAY 2009 EXAM AT POWER FACILITIES 04/20/2009 04/24/2009 Not Applicable EB1-CDBI - COMPONENT DESIGN BASES INSPECTION 8 1, 2 IP 7111121 Component Design Bases Inspection 05/04/2009 05/08/2009 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 05/18/2009 05/22/2009 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/01/2009 06/05/2009 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/15/2009 06/19/2009 Baseline Inspections OL EXAM - INITIAL EXAM - WEEK 1 4 1 V23306 MCGUIRE/MAY 2009 EXAM AT POWER FACILITIES 05/11/2009 05/15/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 2 4 1 V23306 MCGUIRE/MAY 2009 EXAM AT POWER FACILITIES 05/18/2009 05/22/2009 Not Applicable PSB1-RP - RADIATION PROTECTION PUBLIC BASELINE INS 4 1, 2 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 06/08/2009 06/12/2009 Other Routine 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 06/08/2009 06/12/2009 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 06/08/2009 06/12/2009 Baseline Inspections 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 06/08/2009 06/12/2009 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 06/08/2009 06/12/2009 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 McGuire 09/02/2008 11:26:05 Inspection / Activity Plan Report 22 09/01/2008 - 12/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RADIATION PROTECTION PUBLIC BASELINE INS 4 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 06/08/2009 06/12/2009 Baseline Inspections 1, 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 06/08/2009 06/12/2009 Baseline Inspections EB3HS - HEAT SINK 2 1, 2 IP 7111107B Heat Sink Performance 07/13/2009 07/17/2009 Baseline Inspections PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 1, 2 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 08/17/2009 08/21/2009 Baseline Inspections 1, 2 IP 7111401 Exercise Evaluation 08/17/2009 08/21/2009 EP Baseline Inspection 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 08/17/2009 08/21/2009 EP Baseline Inspection 1, 2 IP 71151 Performance Indicator Verification 08/17/2009 08/21/2009 Baseline Inspections EB3ISI - UNIT 2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 09/14/2009 09/18/2009 Baseline Inspections EB3TI172 - TI-172 RCS DM BUTT WELDS 1 2 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 09/14/2009 09/18/2009 Generic Safety Inspectio This report does not include INPO and OUTAGE activities.