March 30, 2006 LICENSEE: Nuclear Management Company, LLC FACILITY: Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE MARCH 23, 2006, PUBLIC MEETING TO DISCUSS THE POINT BEACH END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On March 23, 2006, the Nuclear Regulatory Commission (NRC) held a public meeting at the Two Creeks Town Hall in Two Creeks, Wisconsin. The meeting was between NRC Region III management and Nuclear Management Company (NMC) representatives to discuss the NRCs assessment of Point Beachs safety performance for the period from January 1 through December 31, 2005. The meeting notice and NRC presentation slides can be found in ADAMS as ML060670316 and , respectively. A list of NRC and licensee meeting participants can be found in the attached Enclosure.

The NRC began the meeting with an overview of the NRCs Reactor Oversight Process (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of Point Beachs performance in the calendar year 2005, which was documented in the March 2, 2006, end-of-cycle assessment letter. As part of the regulatory performance meeting, NMC responded to the NRCs assessment and briefly discussed efforts to continue improvement in the engineering area. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

/RA/

Patrick L. Louden, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27

Enclosure:

As stated DISTRIBUTION:

See next page

March 30, 2006 LICENSEE: Nuclear Management Company, LLC FACILITY: Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE MARCH 23, 2006, PUBLIC MEETING TO DISCUSS THE POINT BEACH END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On March 23, 2006, the Nuclear Regulatory Commission (NRC) held a public meeting at the Two Creeks Town Hall in Two Creeks, Wisconsin. The meeting was between NRC Region III management and Nuclear Management Company (NMC) representatives to discuss the NRCs assessment of Point Beachs safety performance for the period from January 1 through December 31, 2005. The meeting notice and NRC presentation slides can be found in ADAMS as ML060670316 and , respectively. A list of NRC and licensee meeting participants can be found in the attached Enclosure.

The NRC began the meeting with an overview of the NRCs Reactor Oversight Process (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of Point Beachs performance in the calendar year 2005, which was documented in the March 2, 2006, end-of-cycle assessment letter. As part of the regulatory performance meeting, NMC responded to the NRCs assessment and briefly discussed efforts to continue improvement in the engineering area. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

/RA/

Patrick L. Louden, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27

Enclosure:

As stated DISTRIBUTION:

See next page DOCUMENT NAME: E:\Filenet\ML060900607.wpd o receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME LHaeg:sls PLouden DATE 03/30/06 03/30/06 OFFICIAL RECORD COPY

Nuclear Management Company cc w/encl: F. Kuester, President and Chief Executive Officer, We Generation D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer

Nuclear Management Company ADAMS Distribution:

JLD CFL EMH1 LXR1 RidsNrrDirsIrib GEG KGO CAA1 RGK DRPIII DRSIII PLB1 JRK1

PUBLIC MEETING PRINCIPAL ATTENDEES March 23, 2006 NRC James Caldwell Regional Administrator, Region III Mark Satorius Director, Division of Reactor Projects Patrick Louden Chief, Branch 5, Division of Reactor Projects Robert Krsek Senior Resident Inspector, Point Beach Gregory Gibbs Resident Inspector, Point Beach Michael Kunowski Project Engineer, Division of Reactor Projects Lucas Haeg Reactor Engineer, Division of Reactor Projects Nuclear Management Company, LLC Michael Sellman President and Chief Executive Officer, NMC Douglas Cooper Senior Vice President - Group Operations, NMC Dennis Koehl Site Vice President, Point Beach James McCarthy Site Operations Director, Point Beach Craig Butcher Engineering Director, Point Beach Enclosure