June 2004 Monthly Operating Report for Perry Nuclear Power Plant, Unit 1
ML042030307
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/09/2004
From: Higaki V
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, PY-CEI/NRR-2816L
Download: ML042030307 (3)


Text

FENOC Perry Nuclear Power Plant FENOC10 Center Road PO. Box 97 FirstEnergy Nuclear Operating Company Perry, Ohio 44081 July 9, 2004 PY-CEI/NRR-2816L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:

Attached is the June 2004 Monthly Operating Report for Perry Unit 1. Page 1 is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."

If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.

Very truly yours, Vernon K. Higaki Manager - Regulatory Affairs Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector

OPERATING DATA REPORT UNIT:

Perry DATE:

7/7/04

1.

Docket:

50-440

2.

Unit Name:

Perry Nuclear Power Piant

3.

Reporting Period June 2004

4.

Utility

Contact:

T.

Phelos

5.

Telephone:

440-280-7660

6.

Design Electrical Rating (Net MWe):

7.

Maximum Dependable Capacity (Net MWe):

1260 1235

-This Month Yr-to-Date

8.

Hours Reactor was Critical 638.0 4,064.7

9.

Hours Generator On-Line 618.7 4,034.4

10.

Unit Reserve Shutdown Hours 0.0 0.0

11.

Net Electrical Energy (MWeH) 694.868. 0 4.916.613.0 mulative -

__-C 116,309.4 0.0

.045.025.0 Page 1

-I IIUNIT SHUTDOWNS t

REPORT MONTH - JUNE 2004 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 717104 CONTACT: T. PhelDs TELEPHONE: (440) 280-7660 No.

Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence 1

Hours j2 3

04-01 5/22/04 F

332.65 IA 4

On 5121/04, One of the Emergency Service Water Pumps failed. The plant commenced reactor shutdown at 16:00 on 5/21/04. The unit was taken off line at 08:42 on 5/22/04. The plant remained off line until 6/5/04 at 05:21 when the generator was synchronized to the grid.

SUMMARY

The Peny Nuclear Power synchronized to the grid at 0521 on 6/5/04. 100% power was achieved on 6/12/04 at 1847. The unit remained on line through month's end.
1. TYPE:

F: Forced S: Scheduled

2. REASON:

A - Equipment Failure (explain)

B - Maintenance or Tbst C - Refueling D - Regulatory E - Operating Training &

License Examination F - Administrative I

G - Operational Error (explain)

H - Other (explain) !

3. METHOD:

1-Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2 1