Response to Order EA-03-009 Rev 1, Issuance of First Revised NRC Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
ML041610275
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 03/10/2004
From: Coutu T
Nuclear Management Co
To:
NRC/SECY/RAS
References
NRC-04-036
Download: ML041610275 (2)


Text

N M C" Kewaunee Nuclear Power Plant Committed to Nu ear Operated by Nuclear Management Company, LLC March 10, 2004 NRC-04-036 10 CFR 2.202 Secretary, Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555 KEWAUNEE NUCLEAR POWER PLANT DOCKET 50-305 LICENSE No. DPR-43 RESPONSE TO ORDER EA-03-009 rev1, "ISSUANCE OF FIRST REVISED NRC ORDER (EA-03-009) ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS"

REFERENCES:

1. Letter from Thomas Coutu (NMC) to Secretary, Office of the Secretary of the Commission (NRC), RESPONSE TO ORDER EA-03-009, "ISSUANCE OF ORDER ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS ", dated February 27, 2003.
2. Letter from Thomas Coutu (NMC) to Secretary, Office of the Secretary of the Commission (NRC), 60-DAY RESPONSE TO ORDER EA-03-009, "ISSUANCE OF ORDER ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS", dated June 13, 2003.

By letter dated February 20, 2004, the Nuclear Regulatory Commission (NRC) issued Revised Order EA-03-009, "Issuance of First Revised NRC Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors." Nuclear Management Company, LLC (NMC) hereby consents to the revised order EA-03-009 as written.

pc N490 Highway 42. Kewaunee, Wisconsin 54216-9511 1/2/

Telephone: 920.388.2560 At t/

/??(

I declare under penalty of perjury that the foregoing is true and accurate.

Executed on March 10, 2004.

Thomas Coutu Site Vice-President, Kewaunee Nuclear Power Plant Nuclear Management Company, LLC.

cc:

Regional Administrator, USNRC, Region IlIl Director, Office of Nuclear Reactor Regulation Assistant General Counsel for Materials Litigation and Enforcement Project Manager, USNRC, NRR NRC Resident Inspector, Kewaunee Plant Document Control Desk