ML032750522

From kanterella
Jump to navigation Jump to search
7 to EP-PS-104, Radiation Protection Coordinator (Rpc): Emergency Plan-Position Specific Procedure.
ML032750522
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 09/17/2003
From:
Susquehanna
To:
Document Control Desk, Office of Nuclear Security and Incident Response
References
28401 EP-PS-104, Rev 17
Download: ML032750522 (6)


Text

Sep. 17, 2003 Page 1 of 1 MANUAL HARD COPY DISTRIBUTION DOCUMENT TRANSMITTAL 2003-42351 USER INFORMATION:

GE CH*RO M EMPL#:28401 CA#: 0363 Addre NUCSA2 TRANSMITTAL INFORMATION:

TO: fPTCl'A 09/17/2003 LOCATION: DOCUMENT CONTROL DESK FROM: NUCLEAR RECORDS DOCUMENT CONTROL CENTER

'NUCSA-2)

'<JAHE FOLLOWING CHANGES HAVE OCCURRED TO THE HARDCOPY OR ELECTRONIC MANUAL ASSIGNED TO YOU:

104 - 104 - RADIATION PROTECTION COORDINATOR (RPC):

EMERGENCY PLSN-POSITION SPECIFIC PROCEDURE REMOVE MANUAL TABLE OF CONTENTS DATE: 09/09/2003 ADD MANUAL TABLE OF CONTENTS DATE: 09/16/2003 CATEGORY: PROCEDURES TYPE: EP ID: EP-PS-104 REPLACE: REV:17 REPLACE: REV:17 REMOVE: PCAF 2003-1640 REV: N/A ADD: PCAF 2003-1640 REV: N/A UPDATES FOR HARD COPY MANUALS WILL BE DISTRIBUTED WITHIN 5 DAYS IN ACCORDANCE WITH DEPARTMENT PROCEDURES. PLEASE MAKE ALL CHANGES AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX UPON RECEIPT OF HARD COPY. FOR ELECTRONIC MANUAL USERS, ELECTRONICALLY REVIEW THE APPROPRIATE DOCUMENTS AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX.

AD45

WI V

Tab12 EP-PS-104-12 EMERGENCY EXPOSURE EXTENSION REQUEST DATE / I TIME TEAM TYPE OF DOSE EXTENSION ():

0 Extend to 25 Rem 0 Extend to __ Rem Approved by/date (RPC/DASU): l Approved by/date (ED/RM):

Current _Lifetime year, dose, dose, E-plan Name Soc Sec # Signature mrem mrem Function Signature of volunteer denotes an understanding and an awareness of the risks involved, including the numerical levels of dose at which acute effects of radiation will be incurred and numerical estimates of the risk of delayed effects.

EP-AD-000-1 35, Revision 7, Page 1 of 3

I Tab 12 EP-PS-104-12 ALARA REVIEW Check v A. PERSON-REM ESTIMATION

1. Assess the number of workers 4. Assure all workers have essential, required. productive tasks.
2. Evaluate the use of fewer workers. 5. Assure workers have available exposure.
3. Investigate experience of workers 6. Evaluate criteria for emergency exposure.

selected.

B. PLANNING

1. Preplanning meeting with supervisors 4. Prefabrication considered.

and/or workers required. 5. Evaluate use of remote handling devises

2. Access to and exit from work are or other special tools.

planned. 6. Cold equipment mockupso, rehearsals, or

3. Evaluate staging/setup in accessible other practical exercise.

low dose rate area.

C. EXPOSURE REDUCTION CONTROLS

1. Evaluate need for timekeeping. 7. System or equipment to be drained and
2. Consider use of water bucket flushed.

shielding for carrying hot parts. 8. Assess exposure reduction by permitting

3. Consider use of shielded drums or decay of radiation sources during reactor lead pigs' for carrying hot parts. -shutdown or system isolation.
4. Consider use of temporary shielding 9. Assess the need of communication such as lead wool blankets, lead devices such as hred sets, TV cameras, sheets, or lead bricks. others.

S. Consider use of shadow shields 10. Assess practicality of removing utilizing a portable curtain shield. component from radiation area.

6. System or equipment to be filled with 11. Evaluate use of photographs of as water. installed equipment' to aid in worker briefings.

D. AIRBORNE/CONTAMINATION CONTROL

- 1. Assess need for respiratory protection 3. Assess necessity of area decon before usage against effectiveness of commencement of work.

engineering controls. 4. Containment structure (tent) required.

2. Assess individual's history of internal 5. Portable ventilation system required.

DAC-Hr exposure to airborne 6. Assess need for flooding or draining contamination. rooms.

7. Assess hot particle or fuel fragment migration.

Performed by EP-AD-000-1 35, Revision 7, Page 2 of 3

'a Tab 12 EP-PS-104-12 Provided below are the instructions on how to retrieve an individual's occupational exposure information.

1. Log into NIMS, go to RPDPERX screen.
2. Query the individual.
3. Click on DOSE SUMMARIES button.
4. The screen In Figure 1 will appear.
5. The individual's YEAR-TO-DATE (YTD) dose will be provided as 'NRC PERIOD EXPOSURE' for the current calendar year.

EP-AD-000-1 35, Revision 7, Page 3 of 3

Tab 12 EP-PS-i04-12 Affected Unit Control No.

PROTECTIVE ACTION RECOMMENDATION FORM SUSQUEHANNA STEAM ELECTRIC STATION 3 This is a Drill o This is NOT a Drill Preparer:

The EMERGENCY CLASSIFICATION Is:

0 Unusual Event 0 Alert {I Site Area Emergency 0 General Emergency Basis: EAL #

This represents:

3 Initial Classification Escalation 0 Reduction 0 No Change in the Classification Status Emergency Action(s) Implemented onsite:

o None O Evacuation of non-essential personnel o Local Area Evacuation o KI to onsite personnel " - -

o Site Accountability O Other Bases:

The PROTECTIVE ACTION RECOMMENDATION Is:

O No Protective Action Recommendation Required o Evacuate 0-2 miles and Shelter 2-10 miles 0 Relocation O Evacuate 0-10 miles 0 Control of Access 3 Contamination Controls/Decon o Divert Danville Drinking Water* 0 Other

  • Expected arrival of release at Danville:

This represents: Initial 0 Change 0 No Change in the Protective Action Recommendation EP-AD-000-1 10, Revision 10, Page 1 of 2 (DUPLEX)

Tab 12 EP-PS-104-12 The BASIS for the Protective Action Recommendation Is:

Plant Status Status of Radioactive Release: Event-related release In progress? 3 Yes No Total Site Release Rate Airborne Liquid

< Tech Requirements Limit I 0 0 1

> Tech Requirements Limit 13 3 NOTE: TRM Limits (Cimin): Noble Gas 1.OOE+6; Iodine 1.04E+2; Particulate 7.72 E+2 (Airborne releases) .

Based on: Effluent Monitors 0 Field Measurements 0 Engineering Judgement Data measured In the field confirm release rate estimations: 0 Yes No 0 N/A Weather Conditions: Wind Speed -*Wind Direction_

_.1 Dose Projections: TEDE > 1 rem or thyroid CDE >5 rem at 2 miles O TEDE> 1 rem or thyroid CDE >5 rem at EPB E3TEDE< rem and thyroid CDE < 5 rem at-EPB-Other:

Approval: Date/Time:

Emergency Director or Recovery Manager approval required if change in Classification or Protective Action Recommendation.

RPC or DASU apprQval if no change in the Classification or Protective Action Recommendation.

Transmittal: 0 Verbal 0 Electronic 0 Both Communicated To:

NAME AGENCY DATE/TIME EP-AD-000-1 10, Revision 10, Page 2 of 2 (DUPLEX)