August 26, 2003 Mr. Mark E. Warner Site Vice President c/o Mr. James M. Peschel FPL Energy Seabrook, LLC Seabrook Station P.O. Box 300 Seabrook, NH 03874
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
SEABROOK STATION
Dear Mr. Warner:
On July 30, 2003, the NRC staff completed its mid-cycle plant performance review of Seabrook Station. The mid-cycle reviews for Seabrook Station involved the participation of all technical divisions in evaluating performance for the first half of the calendar year 2003 assessment cycle.
The process included a review of performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Plant performance of Seabrook Station for the most recent quarter was within the Licensee Response Column of the NRC Action Matrix based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only baseline inspections at your facility through September 30, 2004.
The enclosed inspection plan details the inspections scheduled through September 30, 2004. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspectors arriving onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The last six months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Mr. Mark E. Warner 2
If circumstances arise which necessitate our changing the inspection plan, we will contact you to discuss the change as soon as possible. Please call me at (610) 337-5233 with any questions regarding this letter or the inspection plan.
Sincerely,
/RA/
Brian J. McDermott, Chief Projects Branch 6 Division of Reactor Projects Docket No.:
05000443 Licensee No.: NPF-86
Enclosure:
Seabrook Inspection / Activity Plan
Mr. Mark E. Warner 3
cc w/encl:
J. A. Stall, FPL Senior Vice President, Nuclear & CNO J. M. Peschel, Manager - Licensing G. F. St. Pierre, Station Director - Seabrook Station R. S. Kundalkar, FPL Vice President - Nuclear Engineering D. G. Roy, Nuclear Training Manager - Seabrook Station J. Devine, Polestar Applied Technology D. Bliss, Director, New Hampshire Office of Emergency Management D. McElhinney, RAC Chairman, FEMA RI, Boston, Mass R. Backus, Esquire, Backus, Meyer and Solomon, New Hampshire D. Brown-Couture, Director, Nuclear Safety, Massachusetts Emergency Management Agency S. McGrail, Director, Massachusetts Emergency Management Agency R. Hallisey, Director, Dept. of Public Health, Commonwealth of Massachusetts M. Metcalf, Seacoast Anti-Pollution League D. Tefft, Administrator, Bureau of Radiological Health, State of New Hampshire S. Comley, Executive Director, We the People of the United States W. Meinert, Nuclear Engineer, Massachusetts Municipal Wholesale Electric company R. Shadis, New England Coalition Staff P. Brann, Assistant Attorney General M. S. Ross, Attorney, Florida Power & Light Company Office of the Attorney General Town of Exeter Board of Selectmen Institute of Nuclear Power Operations (INPO)
Mr. Mark E. Warner 4
Distribution w/encl: (VIA E-MAIL)
H. Miller, RA J. Wiggins, DRA J. Jolicoeur, OEDO J. Clifford, NRR V. Nerses, NRR B. McDermott, DRP K. Jenison, DRP G. Dentel, SRI - Seabrook Director, DRS DRS Branch Chief (5)
T. Moslak, DRS P. Frechette, DRS N. McNamara, DRS B. Platchek, DRP Region I Docket Room (with concurrences)
RidsNrrDipmIipb DOCUMENT NAME: G:\\BRANCH6\\ROP Assessments\\ROP4 Mid Cycle July 2003\\Seabrook ROP4 Mid-Cycle Letter.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME KJenison/by teleconference BMcDermott/BJM DATE 08/26/03 08/26/03 OFFICIAL RECORD COPY
Seabrook Inspection / Activity Plan 06/29/2003 - 10/02/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 08/26/2003 13:24:34 Report 22 1
- PUB RAD SAFETY - REMP Baseline Inspections 08/25/2003 08/29/2003 Radiological Environmental Monitoring Program IP 7112203 1
1 71114
- EP PROGRAM INSP & PI VERIFICATION Baseline Inspections 09/21/2003 09/25/2003 Alert and Notification System Testing IP 7111402 1
Baseline Inspections 09/21/2003 09/25/2003 Emergency Response Organization Augmentation Testing IP 7111403 1
Baseline Inspections 09/21/2003 09/25/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1
Baseline Inspections 09/21/2003 09/25/2003 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1
Baseline Inspections 09/21/2003 09/25/2003 Performance Indicator Verification IP 71151 1
1 7111108P
- INSERVICE INSPECTION Safety Issues 10/13/2003 10/17/2003 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02)
Baseline Inspections 10/13/2003 10/17/2003 Inservice Inspection Activities - PWR IP 7111108P 1
1 71121.02
- OCC RAD SAFETY - ALARA Baseline Inspections 10/20/2003 10/24/2003 ALARA Planning and Controls IP 7112102 1
2 7111111B
- L.O.REQUALIFICATION PROGRAM Baseline Inspections 11/17/2003 11/21/2003 Licensed Operator Requalification IP 7111111B 1
5 7111117B
- PERMANENT PLANT MODS Baseline Inspections 01/12/2004 01/16/2004 Evaluation of Changes, Tests, or Experiments IP 7111102 1
Baseline Inspections 01/12/2004 01/16/2004 Permanent Plant Modifications IP 7111117B 1
1 7112102
- OCC RAD SAFETY Baseline Inspections 05/17/2004 05/21/2004 ALARA Planning and Controls IP 7112102 1
1 7112201
- PUB RAD SAFETY - RETS Baseline Inspections 07/12/2004 07/16/2004 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1
1 7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 08/02/2004 08/06/2004 Radioactive Material Processing and Transportation IP 7112202 1
3 71152B
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 09/13/2004 09/17/2004 Identification and Resolution of Problems IP 71152B 1
Baseline Inspections 09/27/2004 10/01/2004 Identification and Resolution of Problems IP 71152B 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.