PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 OPSEG LR-N11-0267 August 27, 2011 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Nuclear Generating Station Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311 Hope Creek Generating Station Renewed Facility Operating License No. NPF-57 NRC Docket No. 50-354 Nuclear LLC
Subject:
Work Hour Controls Before and After a Hurricane Emergency Declaration
Reference:
EGM-09-008, "Enforcement Guidance Memorandum - Dispositioning Violations of NRC Requirements for Work Hour Controls Before and Immediately After a Hurricane Emergency Declaration," dated September 24,2009 PSEG Nuclear LLC has determined sequestering station personnel may be required before and after a hurricane emergency declaration (i.e., when the provisions of 10 CFR 26.207(d) do not apply).
Therefore, consistent with the conditions specified in the referenced Enforcement Guidance Memorandum, PSEG hereby commits to request an exemption from 10 CFR 26.205(c) and (d) before the onset of the next hurricane season, as established by the National Oceanic and Atmospheric Administration's National Hurricane Center (i.e., before December 1, 2011).
Should you have any questions regarding this transmittal, please contact me at (856) 339-1466.
Qj ~~. ~-- ~~f Paul R. Duke, Jr.
\\
Licensing Manager PSEG Nuclear LLC
Document Control Desk LR-N11-0267 August 27, 2011 Page 2 of 2 c
Mr. W. Dean, Administrator - Region I Mr. R. Ennis, Project Manager, NRC USNRC Senior Resident Inspector - Salem (X24)
USNRC Senior Resident Inspector - Hope Creek (X24)
Mr. P. Mulligan, Manager IV - NJBNE Mr. H. Berrick, Salem Commitment Tracking Coordinator Mr. K. Yearwood, Hope Creek Commitment Tracking Coordinator Mr. L. Marabella, Corporate Commitment Tracking Coordinator