L-2012-379, Supplement to License Amendment Request No. 220 Permanent Alternate Repair Criteria (H) for Steam Generator Expansion Region

From kanterella
(Redirected from L-2012-379)
Jump to navigation Jump to search

Supplement to License Amendment Request No. 220 Permanent Alternate Repair Criteria (H) for Steam Generator Expansion Region
ML12307A431
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/18/2012
From: Kiley M
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-2012-379
Download: ML12307A431 (4)


Text

Florida Power & Light Company, 9760 S.W. 344 Street, Florida City, FL 33035 FPL.

October 18, 2012 POWERING TODAY.

L-2012-379 EMPOWERING TOMORROW.

10 CFR 50.90 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001 Re:

Turkey Point Nuclear Generating Station Units 3 and 4 Docket Nos.50-250 and 50-251 Supplement to License Amendment Request No. 220 Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region

Reference:

1. Florida Power and Light Company (FPL) letter L-2012-077, "Turkey Point Nuclear Generating Station Units 3 and 4 License Amendment Request No. 220 - Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region," April 30, 2012.
2. Florida Power and Light Company (FPL) letter L-2012-373, "Supplement to Turkey Point Nuclear Generating Station Units 3 and 4 License Amendment Request No. 220 -

Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region,"

October 10, 2012.

Per Florida Power and Light Company (FPL) letter L-2012-077 (Reference 1) and pursuant to 10 CFR 50.90, FPL requested an amendment to the Technical Specifications (TS) of Renewed Facility Operating Licenses DPR-31 and DPR-41 for Turkey Point Units 3 and 4 to permanently revise TS 6.8.4.j, Steam Generator (SG) Surveillance Program, to exclude portions of the SG tube below the top of the SG tubesheet from periodic tube inspections.

FPL letter L-2012-373 (Reference 2) supplemented the Reference I submittal clarifying Regulatory Commitment Number 2 in Enclosure 5 of L-2012-077. Based on discussions with the Staff, a revision to Regulatory Commitment Number 2 is required. The attachment to this letter replaces Enclosure 5 of L-2012-077 in its entirety. The revision to Regulatory Commitment Number 2 does not impact the no significant hazards consideration determination previously submitted by Reference 1.

Please contact Mr. Robert Tomonto, Licensing Manager, at 305-246-7327 if there are any questions.

too(

an FPL Group company

Turkey Point Nuclear Generating Station Units 3 and 4 L-2012-379 Docket Nos.50-250 and 50-251 Page 2 Supplement to License Amendment Request No. 220 Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region I declare under penalty of perjury that the foregoing is true and correct.

Executed on October

/.1?, 2012.

Very truly yours, Michael W.Kky Site Vice President Turkey Point Nuclear Plant

Attachment:

Revised L-2012-077 Enclosure 5, List of Regulatory Commitments cc:

Regional Administrator, Region II, USNRC USNRC Project Manager, Turkey Point Senior Resident Inspector, USNRC Bureau of Radiation Control Chief, Florida Department of Health

,..Turkey Point Nuclear Generating Station Units 3 and 4 Docket Nos.50-250 and 50-251 Supplement to License Amendment Request No. 220 Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region L-2012-379 Attachment Page 1 ENCLOSURE 5 TO L-2012-077 Page 1 LIST OF REGULATORY COMMITMENTS FOR THIS REQUEST

,.Turkey Point Nuclear Generating Station Units 3 and 4 Docket Nos.50-250 and 50-251 License Amendment Request No. 220 Permanent Alternate Repair Criteria (H*) for Steam Generator Expansion Region L-2012-379 Attachment Page 2 ENCLOSURE 5 TO L-2012-077 Page 2 Turkey Point Units 3 & 4 License Amendment Request for Permanent Alternate Repair Criteria (H*) for Steam Generator Tubesheet Expansion Region The following commitments, approved by Amendments 241 and 236 and incorporating the H* leak factor proposed in this License Amendment Request, will continue to remain in place (these are not new commitments):

REGULATORY COMMITMENTS IMPLEMENT Turkey Point Units 3 and 4 commit to monitor for tube At each scheduled slippage as part of the steam generator tube inspection inspection required by program.

the Steam Generator Program Turkey Point Units 3 and 4 commit to the following:

An administrative 2

Turkey Point Units 3 and 4 will apply a factor of 1.82 to the operational leakage limit normal operating leakage associated with the tubesheet associated with the expansion region in the condition monitoring (CM) and Permanent Alternate operational assessment (OA). Specifically, for the CM Repair Criteria (PARC) assessment, the component of operational leakage from the and the 1.82 leakage prior cycle from below the H* distance will be multiplied by a factor will be established factor of 1.82 and added to the total accident leakage from any in the CMOA starting other source and compared to the allowable accident induced with the Unit 4 Cycle 27 leakage limit. For the OA, the difference between the RFO and the Unit 3 allowable accident induced leakage and the accident induced Cycle 27 RFO.

leakage from sources other than the tubesheet expansion region will be divided by 1.82 and compared to the observed operational leakage. An administrative operational leakage limit will be established to not exceed the calculated value.