Information Notice 1991-19, Steam Generator Feedwater Distribution Piping Damage
| ML031190553 | |
| Person / Time | |
|---|---|
| Issue date: | 03/12/1991 |
| From: | Rossi C Office of Nuclear Reactor Regulation |
| To: | |
| References | |
| IN-91-019, NUDOCS 9103060156 | |
| Download: ML031190553 (8) | |
'
-
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON,'D.C. 20555 March 12, 1991.
NRC INFORMATION NOTICE NO. 91-19: 'STEAM GENERATOR FEEDWATER DISTRIBUTION
PIPING DAMAGE
Addressees
All holders of operating licenses or construction permits for pressurized water
reactors (PWRs).'
Purpose
This information notice is intended to alert addressees to potential problems- resulting from degradation of feedwater distribution piping in steam generators
due to thermal stress, cracking, erosion and corrosion. Depending on the
design of the steam generator feedwater system, these problems may affect
operation of the auxiliary feedwater. system. It is expected that recipients
will review the information for'applicability to their facil.ities and consider
actions,-as appropriate, to avoid'similar problems.
However, suggestions
contained in this information notice'do not constitutekRC requirements;
therefore, no specific action or written response is required...
Background
The degradation noted below of the feedwater distribution system piping in the
steam generators at San Onofre Units 2 and 3 may be applicable to Combustion
Engineering steam generator designs predating the System 80 design and to
similar designs in other-steam generators at.other nuclear-power plants'. This
matter is considered safety-significant because the feedwater distribution
system piping degradation may affect the delivery of auxiliary feedwater flow
in some of these steam generators and because of the potential for consequen- tial damage to the steam generator tubes from resulting debris. The NRC has
issued several generic communications dealing with one or more aspects'of such
degradation (Attachment 3)..
At San Onofre Units 2 and 3, both main feedwater and auxiliary feedwoter enter.
the steam generators through a feedwater nozzle. The feedwater enter'sa.
distribution box and 12-inch diameter pipi'ng (feedring) that distributes the
flow through top-mounted discharge elbows (J-tubes) around the periphery of the
steam generator shell (Figure 1). .The feedring is attached by two U-bolts'at
each of four supports that are welded to the shell wall. A 3-inch elbow and.
tee vent assembly is attached to the'upper portion of the'innermost (toward the
interior of the steam generator)'end of the distribution box (Figure 2).
-
I
9103060156 I.
P
D
~ ~ '. OL
~ 4 ce
h I
.Ro03k
IN 91-19 March 12, 1991 Combustion Engineering originally designed the distribution box without the
vent assembly.
However, in 1980 during preoperational testing at San Onofre
Unit 2, a test of the auxiliary feedwater system caused a partial vacuum within
both halves of the feedring in one of the steam generators, and the feedring
collapsed. The licensee, Southern California Edison Co., determined that the
inadequate flow area of the discharge elbows and the relatively thin-walled
Schedule 40 piping constituting the feedring had contributed to the feedring
collapse. Corrective actions included replacing most of the feedring with
Schedule 120 piping (except for 9-inch segments on each side of the distri- bution box), enlarging the diameter of the discharge elbows from 1.5 inches to
3.5 inches, and installing the vent assembly on the distribution box.
Description of Circumstances
San Onofre Unit 3:
On May 10, 1990, the licensee found several pieces of carbon steel debris
during a routine inspection of the secondary side of the tubesheet of one steam
generator (LER 50-362/90-05-01).
During further inspection of the internal
components of this and the other steam generator, the licensee found material
missing from the lower portion of the feedring at its intersection with the
distribution box, surface cracks in the heat-affected zone at the toe of the
weld at that intersection, erosion and corrosion indications on the interior
surfaces of the distribution boxes, erosion of the vent assemblies, NT" section
tops missing from the vent assemblies, and deformation of several U-bolt
supports.
San Onofre Unit 2:
On July 23, 1990, the licensee shut down Unit 2 to perform a similar inspec- tion.
The damage found was significantly less than on Unit 3. No material was
found missing from the distribution box-feedring junction. One U-bolt was
fractured.
Discussion:
The licensee determined the root cause contributing to the degradation of the
feedwater distribution system piping to be inadequate design of the feedring
and feedring supports. The design did not adequately consider the thermal
stresses resulting from normal operating conditions, in particular the batch
process of auxiliary feedwater addition during startup operations.
In addi- tion, the design of the vent assembly had not properly considered the potential
for erosion and corrosion resulting from localized high velocity flow. The
corrective actions taken by the licensee included replacing the remaining
Schedule 40 piping material with Schedule 120 piping material, replacing the
distribution box-feedring weld configuration with weld-o-let forgings, removing
the distribution box vents from the design, repairing local thinning of the
distribution box by weld buildup and removal of local interior surface
discontinuities, modifying the feedring supports to provide flexibility for
thermal expansion, and using stronger U-bolts. The licensee had previously
modified the auxiliary feedwater system to provide continuous feeding of the
steam generator rather than the batch feeding that was used during startup
operations.
&
IN 91-19 March 12, 1991 Combustion Engineering originally designed the distribution box without the
vent assembly. However, in 1980 during preoperational testing at San Onofre
Unit 2, a test of the auxiliary feedwater system caused a partial vacuum within
both halves of the feedring in one of the steam generators, and the feedring
collapsed.
The licensee, Southern California Edison Co., determined that the
inadequate flow area of the discharge elbows and the relatively thin-walled
Schedule 40 piping constituting the feedring had contributed to the feedring
collapse. Corrective actions included replacing most of the feedring with
Schedule 120 piping (except for 9-inch segments on each side of the distri- bution box), enlarging the diameter of the discharge elbows from 1.5 inches to
3.5 inches, and installing the vent assembly on the distribution box.
Description of Circumstances
San Onofre Unit 3:
On May 10, 1990, the licensee found several pieces of carbon steel debris
during a routine inspection of the secondary side of the tubesheet of one steam
generator (LER 50-362/90-05-01). During further inspection of the internal
components of this and the other steam generator, the licensee found material
missing from the lower portion of the feedring at its intersection with the
distribution box, surface cracks in the heat-affected zone at the toe of the
weld at that intersection, erosion and corrosion indications on the interior
surfaces of the distribution boxes, erosion of the vent assemblies, 'T" section
tops missing from the vent assemblies, and deformation of several U-bolt
supports.
San Onofre Unit 2:
On July 23, 1990, the licensee shut down Unit 2 to perform a similar inspec- tion. The damage found was significantly less than on Unit 3. No material was
found missing from the distribution box-feedring Junction.
One U-bolt was
fractured.
Discussion:
The licensee determined the root cause contributing to the degradation of the
feedwater distribution system piping to be inadequate design of the feedring
and feedring supports. The design did not adequately consider the thermal
stresses resulting from normal operating conditions, in particular the batch
process of auxiliary feedwater addition during startup operations. In addi- tion, the design of the vent assembly had not properly considered the potential
for erosion and corrosion resulting from localized high velocity flow.
The
corrective actions taken by the licensee included replacing the remaining
Schedule 40 piping material with Schedule 120 piping material, replacing the
distribution box-feedring weld configuration with weld-o-let forgings, removing
the distribution box vents from the design, repairing local thinning of the
distribution box by weld buildup and removal of local interior surface
discontinuities, modifying the feedring supports to provide flexibility for
thermal expansion, and using stronger U-bolts. The licensee had previously
modified the auxiliary feedwater system to provide continuous feeding of the
steam generator rather than the batch feeding that was used during startup
operations.
-
e
IN 91-19 March 12, 1991 On September 20, 1990, the steam generator vendor, Combustion Engineering, issued an information bulletin (Combustion Engineering Infobulletin 90-04,
- Feedwater Distribution System Degradation"), recommending that its client
utilities perform a baseline inspection during their next refueling outage to
detect wall thinning in the feedwater distribution system.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact one
of the technical contacts listed below or the appropriate NRR project manager.
Charles
ssi, Direct r
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contacts: Vern Hodge, NRR
(301) 492-1861
Lawrence E. Kokajko, NRR
(301) 492-1380
Attachments:
1. Figure 1. Top View of the Feedwater Distribution Piping
2. Figure 2. Side View of the Feedwater Distribution Piping
3. List of References
4. List of Recently Issued NRC Information Notices
/
-
's /
s
I
4.
Feedwatmr Nozdle
VFeedwate
Pipe
N
Cl
U-Bolts
",.9Q
Support
-
Ste m Geneftor
Shen
J-Tubee
C,
Figure 1: Top View of the Feedwater DistRmlion Piping
D. s
at
'0 =
-4 t A40
C
=
_~
I."
I
=
_" I-A
-A_
-iN X
-s W
)
Steam Generator Shell
Tanrsition
Thermal
Dbtributlon
Box
Typical
J-Tubes
CI
Q
IIF
Auxiliary
P
'ng
Connection
V/
bedwavr
Piping
r,
,,Wefds,
"a
Feedring
Crack-Initiated
Erosion
-
Support
'N support
Welded to
Steam
Generator
Shen
(Center
Support
Shown)
C
Figure 2: Side View of the Feedwater Distribution P
iping
rs os 2~
'
t-
30
to
-
C
o rto oD
Mto M
,
.
Attachment 3
March 12, 1991 LIST OF REFERENCES
1. Bulletin No. 87-01: 'Thinning of Pipe Walls in Nuclear Power Plants,"
July 9, 1987
2. Bulletin No. 79-13: "Cracking in Feedwater System Piping," June 25, 1979
3. Ibid., Revision No. 1:
"Cracking in Feedwater System Piping,"
August 30, 1979
4.
Ibid., Revision No. 2:
"Cracking in Feedwater System Piping,"
October 16, 1979
5. Generic Letter No. 89-08:
"Erosion/Corrosion-Induced Pipe Wall Thinning,"
May 2, 1989
6. Generic Letter No. 79-20: Untitled, on Cracking In Feedwater Lines,
May 25, 1979
7. Information Notice No. 88-17: "Summary of Responses to NRC Bulletin 87-01,
'Thinning of Pipe Walls in Nuclear Power Plants,'" April 22, 1988
8.
Information Notice No. 87-36: "Significant Unexpected Erosion of Feedwater
Lines," August 4, 1987
9.
Information Notice No. 86-106: "Feedwater Line Break," December 16, 1986
10.
Ibid., Supplement 1: "Feedwater Line Break," February 13, 1987
11.
Ibid., Supplement 3: "Feedwater Line Break," November 10, 1988
Attachment 4
March 12, 1991 LIST OF RECENTLY ISSUED
NRC INFORMATION NOTICES
Information
Date of
Notice No.
Subject
Issuance
Issued to
91-18
90-25, SIpp. 1
91-17
91-16
91-15
91-14 High-Energy Piping Failures
Caused by Wall Thinning
Loss of Vital AC Power with
Subsequent Reactor Coolant
System Heat-Up
Fire Safety of Temporary
Installations or Services
linmonitored Release Pathways
from Slightly Contaminated
Recycle and Recirculation
Water Systems at A Fuel
Facility
Incorrect Configuration of
Breaker Operating Springs In
General Electric AK-Series
Metal-Clad Circuit Breakers
Recent Safety-Related Incidents
at Large Irradiators
Inadequate Testing of Emergency
Diesel Generators (EDGs)
Potential Loss of Net Positive
Suction Head (NPSH) of Standby
Liquid Control System Pumps
03/12/91
All holders of 0Ls or
CPs for nuclear power
reactors.
03/11/91
All holders of OLs or
CPs fon nuclear power
reactors.
03/11/91
All holders of OLs or
CPs for nuclear power
reactors.
03/06/91
All fuel cycle
facilities.
03/06/91
All holders of OLs or
CPs for nuclear power
reactors.
03/05/91
All Nuclear Regulatory
Coninission (NRC)
licensees authorized to
possess and use sealed
sources at large
irradiators.
03/04/91
All holders of OLs
or CPs for nuclear
power reactors.
02/15/91
All holders of OLs
or CPs for boiling
water reactors (BWRs).
91-13
91-12 OL = Operating License
CP = Construction Permit