IE Insp Rept 50-395/82-42 on 820713-15.No Noncompliance Noted.Major Areas Inspected:Followup on Inspecter Identified Items
ML20062H932
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 07/26/1982
From: Barr K, Peery W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20062H918 List:
References
50-395-82-42, NUDOCS 8208160214
Download: ML20062H932 (3)


Text

8 UNITED STATES

-

f 1, NUCLEAR REGULATORY COMMISSION g a REGION 11 o * 101 MARIETTA ST., N.W., SUITE 3100 o ATLANTA, GEORGIA 30303

Report No. 50-395/82-42 Licensee: South Carolina Electric and Gas Company Columbia, SC 29218 Facility Name: Virgil C. Summer Nuclear Station Docket No. 50-395 License No. CPPR-94 Inspection at Summer site near Jenkinsville, South Carolina Inspector: 74,5[E W. W. Peery Date signed Approved by: [ %

K. P. Barr, SettterfChief

'J ( Bv

/ fate' Signed Technical Inspection Branch Division of Engineering and Technical Programs SUMMARY Inspection on July 13-15, 1982 Areas Inspected This routine, unannounced inspection involved 16 inspector-hours on site in the area of followup on inspector identified item Results No violations or deviations were identifie PDR ADOCK 05000395 G PDR

,

'

'

.

.

.

REPORT DETAILS Persons Contacted Licensee Employees

  • 0. W. Dixon, Jr. , Vice President, Nuclear Operations
  • 0. S. Bradham, Station Manager
  • A. R. Koon, Technical Services Coordinator L. A. Blue, Director of Health Physics
  • H. C. Fields, Technical Services Engineer
  • S. S. Howze Nuclear Licensing Engineer P. Davis, HVAC, LSS
  • R. G. Sweet, Quality Assurance G. Guy, Technical Support Engineer Other Organizations
  • C. Bowman, Startup Engineer, Westinghouse NRC Resident Inspector J. L. Skolds
  • Attended exit interview Exit Interview The inspection scope and findings were summarized on July 15, 1982, with those persons indicated in paragraph 1 abov . Licensee Action on Previous Inspection Findings Not inspecte . Unresolved Items Unresolved items were not identified during this inspectio . Inspector Follow-up Items (0 pen)(IFI) 395/82-07-03, Damaged Prefilters - The Reactor Building cleanup HEPA filter bank (XAA-004A and B-H) and Reactor Building Purge HEPA and Charcoal Filter Bank (XAA-012-AH) were examined and all filters, including prefilters, were found to be satisfactory. The damaged prefilters in numerous other filter banks had not been replaced. A licensee representative stated that it is still planned to change these filters in the latter stages of plant preparation for-startu _.. _ __ .._ - . _ . . _ _ . - _ _ . _ . _ _ _ . . . . -. .- _

.

i , 6

,

i i (Closed)(IFI) 395/82-21-02, The solid waste solidification system had been completed and tests of the system were satisfactor The inspector had no further question (Closed)(IFI) 395/82-21-03), Measurements of hood face velocities had

~

!

. been completed. The inspector examined the results of the measurements  :

and the hoods and had no further question !

{ (0 pen)(IFI) 395/82-21-06, Waste Gas System. The inspector reviewed the  ;

results of waste gas system test results as follows: '

GH-1, GH02-H1, Waste Gas Suction and Header Recirculation; GH03-H1, i GH04-H1, Waste Gas Shutdown Tanks; GH06-H1, Waste Gas Traps and Tank i Drain Leak Test; GH05-H3, Waste Gas Recirculation Vent Line Test. Any questions that the inspector had were resolved with Test and Startup l

representatives at the conclusion of the revie >

In response to an NRC 94300 letter, the licensee stated that they did  !

not expect to complete testing of the Catalytic Recombiner packages -

a prior to fuel loadin However, the commitment was made by the . i licensee that the Technical Specification requirements regarding the Catalytic recombiners will be me l

>

,