m Luminant CP-202000460 TXX-20077 August 31, 2020 Steven K. Sewell Senior Director, Engineering & Regulatory Affairs U.S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001
Subject:
References:
Comanche Peak Nuclear Power Plant (CPNPP)
Docket Nos. 50-445 and 50-446 License Renewal Application Submittal Schedule Revision Ref Comanche Peak Nuclear Power Plant (Vistra Operations Company LLC)
P 0. Box 1002 6322 North FM 56 Glen Rose, TX 76043 T 254.897.6113 10 CFR 54
- 1. Letter TXX-15164 dated December 14, 2015, from Rafael Flores to the NRC submitting Comanche Peak Nuclear Power Plant License Renewal Application Submittal Schedule Revision (ML16013A201)
- 2.
NRC Regulatory Issue Summary 2009-006 Importance of Giving NRC Advance Notice of Intent to Pursue License Renewal, dated June 15, 2009 (ML0905407890)
Dear Sir or Madam:
Per Reference 1, Vistra Operations Company LLC ("Vistra OpCo") provided a revised submittal schedule for license renewal application for the Comanche Peak Nuclear Power Plant (CPNPP).
Reference 2 requested that licensees provide a written, voluntary submission of licensee's plans regarding license renewal. The purpose of this letter is to formally notify the NRC of the change to the submittal schedule for CPNPP.
The revised license renewal application submittal date for CPNPP is now scheduled for the fourth quarter of 2022.
This communication contains no new commitments regarding CPNPP Units 1 and 2.
TXX-20077 Page 2 of 2 Should you have any questions, please contact Carl Corbin at (254) 897-0121 or carl.corbin@luminant.com.
c (email) -
Scott Morris, Region IV [Scott.Morris@nrc.gov]
Dennis Galvin, NRR [Dennis.Galvin@nrc.gov]
Steven K. Sewell John Ellegood, Senior Resident Inspector, CPNPP Uohn.Ellegood@nrc.gov]
Neil Day, Resident Inspector, CPNPP [Neil.Day@nrc.gov]