February 8,2013 BW130009 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456, STN 50-457, and 72-73 Regulatory Commitment Change Summary Report The purpose of this report is to provide the Exelon Generation Company, LLC (EGC) "Regulatory Commitment Change Summary Report" for Braidwood Station for commitment changes processed during the period from January 1, 2012 through December 31,2012. Commitment changes are processed in accordance with Nuclear Energy Institute's (NEI) 99-04, Revision 0, "Guidelines for Managing NRC Commitment Changes," dated July 1999 and associated implementing procedures.
For the period from January 1, 2012 through December 31, 2012, there were no commitment changes processed in accordance with NEI 99-04, Revision 0 and associated implementing procedures requiring NRC notification.
Should you have any questions concerning this report, please contact Mr. Chris VanDenburgh, Regulatory Assurance Manager, at (815) 417-2800.
Respectfully, Daniel J. Enright Site Vice President Braidwood Station cc:
NRR Project Manager - Braidwood Station Illinois Emergency Management Agency - Division of Nuclear Safety US NRC Regional Administrator, Region III US NRC Senior Resident Inspector (Braidwood '-"""'V, Illinois Management Agency - Braidwood