ADP CR3, LLC CR3 Decommissioning 15760 West Power Line Street l Crystal River, FL 34428 Page 1 of 2 Billy Reid, Site Executive Cellphone: 865-384-6789 Email: breid@northstar.com 3F0825-01 10 CFR 20, Appendix G August 4, 2025 Ms. Andrea L. Kock Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Rd, Suite 102 King of Prussia, PA
Subject:
Report of Investigation Pursuant to 10 CFR 20, Appendix G Crystal River 3 Nuclear Power Station Docket Numbers 50-302 License Number DPR-72
Dear Madam,
This letter documents the results of an investigation performed with respect to the transportation of 1 shipment by rail car, containing UN3321, LSA -II material, which exceeded the 45 day time limit for notification of receipt by the disposal facility as specified in 10 CFR Part 20, Appendix G, as exempted. The investigation, which was completed on July 31, 2025, determined that the logistics of the rail car was tracked daily during transport by Industrial Construction Environmental Service Group (ICE) rail logistics. The disposal facility, Waste Control Specialists, LLC (WCS), and the Crystal River 3 waste operations personnel received daily updates from the ICE rail tracking report.
10 CFR 20, Appendix G, Requirements for Transfers of Low-Level Radioactive Waste Intended for Disposal at Licensed Land Disposal Facilities and Manifests,Section III.A(9) states for any shipments or any part of a shipment for which acknowledgment of receipt has not been received within the times set forth in this appendix, conduct an investigation in accordance with Section III.E of this appendix.
Section III.E states that any shipment or part of shipment for which acknowledgement is not received within the times set forth in this section must:
- 1. Be investigated by the shipper if the shipper has not received notification or receipt within 20 days after transfer (45 days in accordance with the current exception for CR3 per ML21028A590); and
- 2. Be traced and reported. The investigation shall include tracing the shipment and filing a report with the nearest Commission Regional Office listed in Appendix D to this part.
Each licensee who conducts a trace investigation shall file a written report with the appropriate NRC Regional Office within 2 weeks of completion of the investigation.
Page 2 of 2 Investigation On June 6, 2025, 1 shipment by rail containing UN3321, LSA-II material departed from the Crystal River 3 site at 15760 West Power Line Street in Crystal River, Florida to Waste Control Specialists, LLC in Andrews Texas.
Crystal River 3 and WCS received daily tracking reports from the railroad logistics contractor, ICE, for the waste shipment transported from the Crystal River 3 Site. The location of the subject shipment was verified and traced until receipt at the destination facility. At no time was the shipment lost or in an unknown location. The shipment was placed at the disposal facility by Texas and New Mexico Railway (TXN) on June 28, 2024.
The shipment was released to the first railroad carrier, Florida Northern Railroad (FNOR), on the date identified above. After release in June from the Crystal River 3 site, the shipment was in transport for 52 days before the shipment was received at the disposal facility on July 28, 2025.
Below is the summary for the rail shipment that exceeded the time provided in 10 CFR 20, Appendix G (as exempted). The summary table includes the shipment identification (manifest) number, rail car identification (ID) number, shipment date, date of receipt at the waste disposal facility, and the total number of days the shipment was in transit.
Manifest Number Rail Car ID Number Date Shipped Date Received at Waste Control Specialists, LLC.
Total Days In Transit NS-CR3-25-243 ITFX 8110 6/6/2025 7/28/2025 52 This letter contains no new regulatory commitments.
Should you have any questions concerning this letter, please contact Mr. John T. Jernigan at (352) 342-0792.
Sincerely, Billy Reid Nuclear Executive Cc: NMSS Project Manager Regional Administrator, Region 1 Regional Administrator, Region 2