| Q | CCA | Title |
---|
05000341/FIN-2013403-02 | 2013Q1 | H.2 | Security |
05000341/FIN-2013403-01 | 2013Q1 | H.2 | Security |
05000341/FIN-2013003-01 | 2013Q2 | H.5 | Not Following Plant Documents for Switchyard Modifications |
05000341/FIN-2013003-02 | 2013Q2 | | Respirator Cartridge Storage Life |
05000341/FIN-2013003-03 | 2013Q2 | H.8 | Failure to Maintain Configuration Control During Plant Operation |
05000341/FIN-2013009-01 | 2013Q2 | | Failure to Implement Foreign Material Exclusion Procedure Requirements Adversely Affected the Reliability of the Main Turbine Generator and Caused a Reactor Scram |
05000341/FIN-2013008-01 | 2013Q3 | | Battery Rack Configuration Not in Accordance with Design Basis |
05000341/FIN-2013008-02 | 2013Q3 | | Design Loads for ECCS Suction Strainer Modification Not in Conformance with Design Basis Plant Unique Analysis Report |
05000341/FIN-2013008-03 | 2013Q3 | | Failure to Correct Non-Conservative Technical Specification |
05000341/FIN-2013008-04 | 2013Q3 | | Untimely Resolution of Non-Conservative Battery Technical Specification |
05000341/FIN-2013008-05 | 2013Q3 | | Battery Testing Not in Conformance with Design Standard |
05000341/FIN-2013005-02 | 2013Q4 | | Acceptance Criteria for UHS Level and Temperature Did Not Consider Instrument Uncertainties |
05000341/FIN-2013005-03 | 2013Q4 | H.12 | Failure to Correctly Connect Thermocouple Wiring During Maintenance Resulted in Inoperable Reactor Core Isolation Cooling System Isolation Instrumentation |
05000341/FIN-2013005-05 | 2013Q4 | | Nonconforming Materials Used in EDG Air Coolant Piping System |
05000341/FIN-2013021-01 | 2013Q4 | H.12 | Security |
05000341/FIN-2013005-01 | 2013Q4 | | RHR Pump Seal Cooler Testing Was Not Adequately Implemented |
05000341/FIN-2013005-04 | 2013Q4 | | Evaluation of Apparent Unacceptable Preconditioning of High Pressure Coolant System Air Operated Valve Prior to Stroke Time Testing |